MeyerFire
  • Blog
  • Forum
  • TOOLKIT
    • ALL TOOLS
    • BUY THE TOOLKIT
  • UNIVERSITY
    • ALL COURSES
    • JOIN THE UNIVERSITY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE PREP SERIES
    • PE Old Questions
  • STUDENTS
    • LAND JOB/INTERNSHIPS
    • STUDENT CONNECTOR
  • LOGIN
    • TOOLKIT-ONLY LOGIN
    • UNIVERSITY LOGIN
  • STORE
  • OUR CAUSE
    • ABOUT MEYERFIRE
    • JOB OPENINGS
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT
Picture

Don't Check, Butterfly Valves Limit Max Pressure?

8/28/2026

3 Comments

 
Looking at NFPA 14-2019 A.7.1(b) Typical Two Zone - Wouldn't the system on the 2nd fire pump in series discharge side be limited to 365 psi static pressure (not forgetting the jockey pump added pressure) due to the check & butterfly valve's listed working pressures?

NFPA 14-2019 Section 7.2.1 limits max pressure to 400 psi and Section 7.2.2 says express mains can exceed 400 psi in accordance with material listings (or as approved by AHJ).

From what I can find on the market, Victaulic has the highest listed of those two valves at 365 psi (Vic Check 716 and Vic BFV 765/766).

It seems like a lot of designs rely on the fact that some valves list that you can field test them up to 500 psi or 1-1/2 times one time and are relying on the as approved by the AHJ.

The waterflow switch is listed up to 450 psi and not worried about the pressure gauge.

​Am I just not aware of higher-listed valves?


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
3 Comments

Standpipe for 1-Story Warehouse in IBC 905.4?

8/27/2026

8 Comments

 
I am being told that I need to install a standpipe on my warehouse roof because IBC 905.4 calls out the location of Class I standpipe hose connection in locations where the roof slope is 4 units vertical and 12 units horizontal.

However, my building is a single-story warehouse and doesn't meet the conditions established in section 905.3.1.

​Am I required to put in a standpipe because of Section 905.4?


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
8 Comments

Reason for Differences in Flow Test Results?

8/25/2026

13 Comments

 
We are working on a school project that needed a 1,000 gpm fire pump due to three standpipes.

We initially did a hydrant flow test and had a flow of 425 gpm with a static of 55 psi and residual of 50 psi when we started the design
. By the time it went out to bid and the contractor performed their own test,​ they flowed 354 gpm with a static of 55 and a residual of 50.

In the first test, we got 1215 gpm at 20 psi, and 1012 gpm in the second test. They went to turn on the pump and were only getting 368 gpm when the building inlet pressure was at 20 psi.

We re-did the flow test to see what changed so drastically and again got a static of 51 with residual of 46 at 375 gpm, which would give us 1004 gpm at 20 psi.

We have confirmed the two valves between the street and
the building are fully open, and we only have about 50 feet of 8” pipe, so the pressure drop to the building is negligible, especially at 368 gpm.

We are at a loss for what could be causing such a difference in pressure to the building and such a low flow.

​Has anyone ever run into an issue like this or have any suggestions of what else we could check out?


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
13 Comments

Manual Pump for Old High Rise Standpipe Feed?

7/29/2026

7 Comments

 
Hi everyone, I have some questions regarding old high rise standpipes.

In many old
high-rise buildings, they will have a wet standpipe fed from a gravity tank (or tanks), which is in turn filled by dedicated tank-fill pumps. Some will also have an additional manual fire pump down in the basement that can pressurize the standpipe upwards; I’m figuring just as backup for the existing roof tank reservoir.

First question: Is this type of setup just a relic of the past since it’s just a manual backup pump?

I haven’t found where in modern code it seems to be applicable to this whole setup. At least, it doesn’t seem to have any mention in NFPA 20, even though that’s the main fire pump book.

Second question: All these vintage motors and controllers seem to be
wound-rotor motors, and the controller is speed-controlled via resistor banks.

Is the stepped speed control simply to reduce inrush by ramping one step at a time up to full speed, or are they intended to operate at reduced speeds on purpose?

I’m figuring the modern equivalent to these old setups would likely be a soft-start controller if you’re just looking to reduce inrush, or a VFD controller if you want to run at reduced speeds on purpose. Of course, all of this conjecture is only if such a setup is even relevant to modern code.

Thank you for any insight you can offer!


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
7 Comments

How to Calc Upstream of Manual Standpipe FDC?

7/16/2026

4 Comments

 
When calculating manual standpipe systems per NFPA 14, are there any tips on calculating upstream from the FDC back through the hose lay back to the apparatus?

And I assume even considering the underground supply the apparatus is drawing from?

I know many pumper trucks are rated at 1,500 gpm at 150 psi, but I assume one would need to verify that, and what length, diameter, and type of hose they utilize from the truck to the FDC.

​I see too many calcs that assume an "infinite" water supply if it is supplied by a pumper truck.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
4 Comments

Mandate for Old Standpipe Meeting Old Code?

6/26/2026

8 Comments

 
Where is (or is there) a code or standard provision for an existing/old standpipe system that mandates that the standpipe system must follow the codes (and edition) in which it was originally installed?

Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
8 Comments

Why Aren't Added Standpipe Flows Balanced?

6/19/2026

7 Comments

 
When adding flow of additional standpipes (vertical standpipes with a horizontal connecting main), the NFPA 14 handbook (NFPA 14 10.6.1.2.4) explicitly says that flows shall not be required to be balanced.

I get the logic of balancing the calc, and it's not terribly hard to do - but what's the difference?

Is not balancing the calculation more conservative?

Is it insignificant, and therefore doesn't really matter?

Why aren't we required to balance the calc by code?


Thanks in advance.
​
Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
7 Comments

Where is Hose Allowance for Combined System?

4/30/2026

3 Comments

 
When hose allowance is added to the sprinkler demand on a Class III Standpipe/Sprinkler wet riser, where on the system are the inside and outside flow and pressure allowances input when calculating the system?

NFPA 13 Chapter 19 states that the allowances are not required when calculating a combined system, which appears to contradict NFPA 14 requirements to include them.

In my case, the sprinkler demand is for OH2 (ceiling higher than 40 ft), resulting in a sprinkler demand plus hose allowance that is greater than the standpipe demand.

​If I don’t include hose allowance in the sprinkler calculation as per Chapter 19, this combined system is not equivalent and robust as two independent systems. Any thoughts?


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
3 Comments

Standpipe Allowed to Run In-Between Stair?

4/22/2026

15 Comments

 
Is this an allowed and feasible installation for FHV's that are required to be installed at intermediate landings, to avoid penetrations in a precast stair?

Is there a code basis against this, or any differing recommendations on routing here?

​See image below.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
Picture
15 Comments

Reason Not to Omit Standpipes if Code Allows?

4/15/2026

8 Comments

 
I appreciate this community and thank you in advance. I'm new to the fire protection industry, having been in other building engineering disciplines for many years.

For multiple buildings on a campus using the IBC.

"IBC 905.3.2 Building Area Amendment In buildings exceeding 10,000 square feet (929 m2) in area per story, Class I automatic wet or manual wet standpipes shall be provided where any portion of the building's interior area is more than 200 feet (60,960 mm) of travel, vertically and horizontally, from the nearest point of fire department vehicle access.

Exceptions:
1. Buildings equipped throughout with automatic sprinkler systems installed in accordance with Section 903.3.1.1.
2. Group A-4, A-5, F-2, R-2, S-2 or U occupancies."


Is there any reason not to eliminate the standpipes if the height and occupancy thresholds aren't exceeded?

One of the buildings is a two-story, 60,000 SF building. The path of travel plans shows a 150+ foot range. Does this cause any concern?

I know the standpipes are to assist in manual firefighting ops, but is eliminating them increasing future risks to the occupants?


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
8 Comments

Standpipe Locations with Many Horizontal Exits?

4/8/2026

8 Comments

 
I'm working on a fire protection design for a new apartment building. The architect is adding what they're calling horizontal exits throughout the building, which will increase the number of required standpipes per the local building code (IBC-based, 2025) Section 905.4.

Per the exception to 905.4.2, I do not believe we will need hose connections on both sides of every horizontal exit within the building. I think additional standpipes and hose connections will only be required in the center of the building.

Other than the egress stairwells, where are standpipes and hose connections required to be located?


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
Picture
8 Comments

Create Permanent Test Connection for Standpipe?

4/6/2026

9 Comments

 
I have a client with a 10-story office building/parking garage, a fire pump in the below-grade level, and a combined wet standpipe with a manifold on the roof for testing. The building is getting some age on it, and when performing a flow test from the roof manifold, the roof drains will leak water into the top floor offices.

The question that was posed to me by the building manager was, "Can we tie into the bottom of the standpipe and run a new test connection to the outside at ground level?"

Shooting the water over the side of the building is not really an option, doable, yes, but not really an option.

Just wanting some thoughts on this, my initial response was no, but then I had never been posed with this question either.

​If not, is it possible to permanently tie somewhere else, or conduct the test in a different way?

Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
9 Comments

Basis for Manual Standpipe on Sprinkler System?

3/30/2026

8 Comments

 
We have a consultant showing a 6" wet sprinkler riser routing through the 1st floor of a building, supplying sprinklers, then heading to a stairwell to supply a wet manual standpipe. I am confident that supplying a standpipe downstream of a sprinkler system is not allowed, as there would be no way to fight the fire with hoses without the ability to shut off the sprinkler system, but keep the standpipe live.

Can someone shed some light on the code referring to this in either NFPA 13, 14
, or even FM Global that details standpipes can feed sprinkler systems in a combination setup, but a sprinkler system cannot feed a standpipe?

​Thanks in advance!

Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
8 Comments

Code to Keep Standpipes but Remove Cabinets?

3/24/2026

9 Comments

 
We have an old Convent building (3-stories with long corridors) that currently has a Type III manual wet standpipe system and no sprinklers. They are remodeling and are installing sprinklers throughout, and want to remove the standpipe system.

As the AHJ, I would like to keep the standpipes but remove the hose cabinets, essentially to make it Class I.

Is there a relevant code path to keep the standpipes even though, for new construction, they would not need them?

Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
9 Comments

Is 65 psi Standpipe OK for Highrise Conversion?

2/13/2026

8 Comments

 
Regarding existing high-rises going through an occupancy change (B to R-2), am I correct that all an engineer has to meet is the 65 psi at the top most floor per IEBC 2021 803.3 Exception 1: "A pump shall not be required provided that the standpipes are capable of accepting delivery by fire department apparatus of not less than 250 gallons per minute (gpm) at 65 pounds per square inch (psi) (946 L/m at 448 KPa) to the topmost floor in buildings equipped throughout with an automatic sprinkler system or not less than 500 gpm at 65 psi (1892 L/m at 448 KPa) to the topmost floor in all other buildings. Where the standpipe terminates below the topmost floor, the standpipe shall be designed to meet (gpm/psi) (L/m/KPa) requirements of this exception for possible future extension of the standpipe."

The code section makes no mention of high-rise difference and the commentary states: "Exception 1 allows the installation of a standpipe system without a fire pump if sufficient water with sufficient pressure could be delivered by means of fire department apparatus pumps to the topmost floor of the building. Under this exception, the location of the work area is irrelevant, and the topmost floor must be considered whether the work area is located at the topmost floor or not."

I
can't find anything that an existing building needs to meet the 100 psi requirement of the IBC, and this would trigger the need for a fire pump if I can meet 65 psi already.

Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
8 Comments

OK to Combine Sprinkler/Standpipe Dry System?

12/5/2025

9 Comments

 
Is there an NFPA 13 or 14 restriction for a combined sprinkler - standpipe dry system?

This is an open parking structure. Thanks in advance.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
9 Comments

Dry Standpipe Required for Open Parking Ramp?

12/4/2025

6 Comments

 
I am working on a project that is building and connecting an open parking ramp to an existing building via an open bridge. The open garage will be going next to an existing building (different from the one it will be connecting to).

Does the open parking ramp need a dry standpipe?

It will be just over
69 feet tall, and it doesn't look like there are elevators within the enclosed stairwells from the architect's rendering. I don't have a CAD background to compare to yet.

​Thanks in advance.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
6 Comments

Does Manual Standpipe 5-Year Need Fire Dept.?

11/27/2025

4 Comments

 
In a 3-story building with 3 standpipes, one of which is a combination standpipe/riser, and the standpipes are manual wet, with 50 psi.

On a 5-year test, how do I flow 1000 gpm (no pump) at 100 psi?

Do I involve the fire department?

The old hydraulic plates showed 70-50 at 260 flow. Three years later, they are showing 50-40 at 320 flow.

So I cannot pass this, even though the water supply has diminished.

Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe

4 Comments

Standpipe for Scissor Stair Need 500 or 750 gpm?

11/19/2025

4 Comments

 
For scissor stairs having 2 separate standpipe risers (one of them is a combined sprinkler and standpipe system) running 12 floors, how do we size the pump flow rate required?

Can we argue that we can use
a 500GPM pump since the Risers are in close proximity to each other and are within one stairwell, or should we use a 750GPM pump following the NFPA 14 sizing of 500GPM plus 250 GPM per additional riser?

​Thanks in advance.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
4 Comments

Standpipe Connection On Floor Without Door?

11/6/2025

10 Comments

 
I have a hotel building that requires a standpipe in each of the two staircases. One of the stair shafts has a door to the outside at grade level, but there is no door to the first level inside. The lowest level with an interior door is the second floor, which has its own hose connection.

It doesn't make sense to provide a hose connection at the ground floor, but is there a code basis to support this?

Thanks!


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
10 Comments

Are Standpipe Hydraulic Placards Required?

10/16/2025

12 Comments

 
Standpipe hydraulic placards - are they required?

You don’t see too many of them
, so it would be difficult to find out how much psi max to pump in I don’t see many at the FDCs. Some fire marshals ask for one, others do not. I feel I’m the only one providing them.

NFPA 14 6.8 requires them and tells you what to put on them (2016 to present). I place them at the exterior FDCs, base of standpipes, at the tested valves, and at the fire pump.

Why aren’t the signs enforced?

Are you seeing these regularly?

​Thanks in advance.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
Picture
12 Comments

Where to Discharge a Sub-Grade Express Drain?

10/8/2025

7 Comments

 
In sub-grade parking garages, with PRV fire hose valves/floor controls - for testing purposes, would you connect a PRV fire hose valve to the express drain via hose and pump vertically to get to the exterior grade to discharge?

Are there any issues with this method during testing to consider?

PRV floor control would be hard piped to the express drain and utilize the same pathway to the exterior. Then at the bottom of the express drain has a ball valve, acting as an auxiliary drain only. It can discharge to a gravity drain system, whether storm or sanitary, whatever your local AHJ permits.

Or is everyone trying to discharge into a gravity drain at the bottom of the stairs and hoping to not flood anything?

​Thanks in advance.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
Picture
7 Comments

PRV Options for Combined Sprinkler/Standpipe?

10/6/2025

6 Comments

 
Have 5 stories of parking with about 15 levels of residential floors above. For an enclosed, heated/conditioned garage we can use a wet system.

If we're using Extra Hazard Group 2 with high temp sprinklers or 11.2k sprinklers, which reduces our design area we know we need to account for "0.40 gpm/sqft x 2,000 sq.ft. = 800 gpm demand" at least.

A PRV floor control valve like a 2-1/2" Zurn ZW5004 tops out at 500 gpm per the data sheet.

Would it be possible to utilize two of these floor controls from different stairs and have an interconnected system on those levels?

Or would it be better to utilize to try and separate the garage level sprinkler system from the standpipe for those levels and use a master pressure reducing valve station on ground level to feed the 5 garage levels?

Would a redundant pressure reducing valve at a master pressure reducing valve station be necessary if the sprinkler feed is separated from the standpipe feed for those levels?

Or could I just use a grooved 6" pilot-operated PRV like a Cla-Val 90G-21 (listed for 1763 gpm) before a floor control on garage levels?

(a combined sprinkler/standpipe configuration)

Lots to this, appreciate the feedback in advance.


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
6 Comments

How to Address Fire Pump Surge/Water Hammer?

10/1/2025

6 Comments

 
TL;DR:
How can surge/water hammer forces be managed in very tall high-rise fire protection system using a single high-pressure pump (~365 psi) without exceeding equipment ratings or NFPA limits?

Question:
Trying to pre-plan in my mind for some upcoming pretty tall highrises where design teams would like to utilize 1 pump in lieu of a high/low multi-pump set up.

I'm coming up with a couple of challenges. For the sake of the problem lets assume the static pressure at the fire pump discharge flange is 365 psi. I'm concerned that fire pump starting methods might create shockwaves/water hammer in high-pressure standpipes whether it be at the start of the pump like across-the-line or end of the curve spike like a wye-delta closed might see.

How concerning is creating surge forces that exceed coupling/PRV valve/Pressure Relief Valve listed ratings?

First reaction for many like me has always been to utilize soft-start but electrically with generators soft-start has a much higher load that has to be accounted for in the generator sizing because of the electrical engineers have to size them as across-the-line because of the bypass & 600% FLA.

Maybe they just have to suffer on their design for FPs to be what it needs to be, but am trying to be accommodating where it makes sense.

Is the general method to rely on a main relief valve in these high-pressure systems?

NFPA 14 limits us to 400 psi but I'm not finding pressure relief valves that are listed high enough for the static pressure of the system i.e. cal-val at 300 psi, Victaulic at 350 psi.

Is anyone utilizing anything like an Amtrol Surge-Trol Tank type products?

Maybe VFD controllers to flatten/lower the static pressure?

Some additional concerns in my mind are PRV hose valves have a 400 psi rated value and some couplings for example Victaulic might be rated at 365 psi. I know there are higher rated couplings on the market, like 500 psi, but if my static pressure on the system is 365 psi, I could see a surge force exceeding the rated values (zero math to support that claim).

I'm struggling to quantify the possible surge force values in the design phase and how to handle that. Reading SFPE Handbook of Fire Protection Engineering 5th edition Water Hammer section pg 1407, it's focused mostly on the closing of valves, and still wrapping my head around if those equations can be applicable/same for pump starting forces.

Thanks in advance.

Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
6 Comments

How to Calculate a Class 1 Horizontal Standpipe?

8/13/2025

5 Comments

 
I have a horizontal standpipe Class 1 in a 157,252 sqft warehouse that needs calc'd, but I'm trying to figure out how to go about that.

Per NFPA 14, 2016 edition, it seems to me that you would have the hydraulically most demanding hose valve flow 250-gpm @ 100-psi, and then flow three (3) more hose valves at 250-gpm until I get to a 1000-gpm total. However, Section 7.10.1.2.2 only says to do this up to 3 hose valves total.

What am I doing wrong?


Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
5 Comments
<<Previous
    SUBMIT A QUESTION
    Picture
    Why Sponsor?

    ALL-ACCESS

    Picture
    GET ALL OUR TOOLS

    SUBSCRIBE

    Subscribe and learn something new each day:
    I'm Interested In:

    COMMUNITY

    Top July '26 Contributors
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    SEE LEADERBOARD

    YOUR POST

    SUBMIT A QUESTION

    PE EXAM

    Get 100 Days of Free Sample Questions right to you!
    SIGN ME UP!

    FILTERS

    All
    A1171
    ABA
    ADA
    ASCE 7
    ASME A17.1
    ASTM E1354
    Blog Thread
    Daily Discussion
    Design-documents
    EN 12259-1
    EN 12845
    Explosion Protection
    Explosion-protection-prevention
    Fire Detection And Alarm Systems
    Fire Dynamics
    Flammable And Combustible Liquids
    Flammable-combustible-liquids
    FM Global
    Human-behavior
    IBC
    ICC 500
    IEBC
    IFC
    IMC
    IPC
    IRC
    ISO
    Means Of Egress
    NBC
    NFPA 1
    NFPA 10
    NFPA 101
    NFPA 11
    NFPA 110
    NFPA 1142
    NFPA 1221
    NFPA 13
    NFPA 13D
    NFPA 13R
    NFPA 14
    NFPA 15
    NFPA 16
    NFPA 17A
    NFPA 20
    NFPA 2001
    NFPA 214
    NFPA 22
    NFPA 220
    NFPA 24
    NFPA 241
    NFPA 25
    NFPA 291
    NFPA 30
    NFPA 307
    NFPA 30B
    NFPA 31
    NFPA 33
    NFPA 37
    NFPA 400
    NFPA 409
    Nfpa-415
    Nfpa-45
    Nfpa-495
    NFPA 497
    NFPA 5000
    NFPA 502
    NFPA 54
    NFPA 55
    NFPA 654
    NFPA 68
    NFPA 70
    NFPA 701
    NFPA 72
    NFPA 75
    NFPA 770
    NFPA 82
    NFPA 850
    NFPA 855
    NFPA 90A
    NFPA 92
    NFPA 96
    NICET
    OBC
    OSHA
    Passive Building Systems
    PE Prep Guide
    PE Prep Series
    PE Sample Problems
    Poll
    Smoke Management
    Special Hazard Systems
    UFC 3-600-01
    UFC 3-601-02
    UFC 4-021-01
    UFC 4-211-01
    UPC
    Updates
    Water Based Fire Suppression
    Weekly Exams


    ARCHIVES

    September 2026
    August 2026
    July 2026
    June 2026
    May 2026
    April 2026
    March 2026
    February 2026
    January 2026
    December 2025
    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    November 2016
    October 2016
    July 2016
    June 2016


    PE PREP SERIES

    SEE LEADERBOARD

    SEARCH THE FORUM

    RSS Feed

Picture
​Home
Our Cause
The Blog
The Forum
PE Exam Prep
The Toolkit

MeyerFire University
​Pricing
Login
​Support
Contact Us
Picture

MeyerFire.com is a startup community built to help fire protection professionals shine.
Our goal is to improve fire protection practices worldwide. We promote the industry by creating helpful tools and resources, and by bringing together industry professionals to share their expertise.

​MeyerFire, LLC is a NICET Recognized Training Provider and International Code Council Preferred Education Provider.

All text, images, and media ​Copyright © 2016-2025 MeyerFire, LLC

We respect your privacy and personal data. See our Privacy Policy and Terms of Service. 
The views, opinions, and information found on this site represent solely the author and do not represent the opinions of any other party, nor does the presented material assume responsibility for its use. Fire protection and life safety systems constitute a critical component for public health and safety and you should consult with a licensed professional for proper design and code adherence.

Discussions are solely for the purpose of peer review and the exchange of ideas. All comments are reviewed. Comments which do not contribute, are not relevant, are spam, or are disrespectful in nature may be removed. Information presented and opinions expressed should not be relied upon as a replacement for consulting services. Some (not all) outbound links on this website, such as Amazon links, are affiliate-based where we receive a small commission for orders placed elsewhere.

  • Blog
  • Forum
  • TOOLKIT
    • ALL TOOLS
    • BUY THE TOOLKIT
  • UNIVERSITY
    • ALL COURSES
    • JOIN THE UNIVERSITY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE PREP SERIES
    • PE Old Questions
  • STUDENTS
    • LAND JOB/INTERNSHIPS
    • STUDENT CONNECTOR
  • LOGIN
    • TOOLKIT-ONLY LOGIN
    • UNIVERSITY LOGIN
  • STORE
  • OUR CAUSE
    • ABOUT MEYERFIRE
    • JOB OPENINGS
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT