What is the industry standard or method used for determining the design area size in order to do the hydraulic calculations for Window Sprinklers in terms of the "Adjacent Sprinklers?"
What is the definition of "Adjacent Sprinklers?" Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
5 Comments
When dealing with combustible soffits, what are the conditions where a soffit is big enough to warrant a sprinkler inside?
In our case, we have wood constructed soffits with sprinkler protection below and adjacent to the soffit. Thanks in advance. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe For NFPA 13D and a single family home of 1,000 sq ft, what is the optimal k-factor I should be considering?
In this particular project, we don't have a city water supply but we do have a good well. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe How would you recommend protecting a dry room for battery operations, such as battery testing or packaging?
I've been designing these with dry systems but was curious if there are any codes to omit sprinklers, or if anyone uses clean agent systems? If you use something alternatively, why do you go that direction? Moderator's Note: Dry Rooms for batteries have less moisture to avoid corrosion and any chemical reaction for the batteries, which would degrade or reduce performance. Very low moisture is the key for a dry room for batteries. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe I have a sprinkler system in a 75,000 sqft self-storage facility.
There are upright sprinklers that are within 2" of a vertical support Unistrut that is used to separate storage spaces. Would this be considered obstructed? What is the code-basis for evaluating a vertical obstruction like this? If a duct detector is installed, and the mechanical unit has a capacity of less than 2,000 CFM, it is required by code for the duct detector to be connected to the fire alarm panel?
Alternatively, removing the detectors can be considered in this situation. Looking for relevant code and standard basis. We're under the 2021 IFC, 2021 IBC, and 2019 NFPA 72. Thank you! Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe Does anybody have experience with locating diesel fire pump fuel tanks in exterior locations where the local ambient temperature can drop to below freezing point?
We have an unavoidable situation where we have to locate the fuel tank outside the pump room and we're hoping not to have to build a heated enclosure. NFPA 20 seems to require a heated enclosure, but FM not so much. I am aware that condensation and fuel deterioration are issues to be dealt with, but I was thinking maybe good quality thermal lag of the tank and feed/return fuel piping may be sufficient with just a roof structure above the fuel tank. What are your thoughts on this? any thanks in advance for your thoughts and advice Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe I have a 35' tall, 79,103 ft², non-combustible building, which is a cooler in a cheese factory. There are two dry systems at the ceiling uses CMDA heads. There are single and double row racks throughout the cooler. The top of the rack 22' top of storage is roughly 26'. The racks have a single layer of 5.6K in-rack sprinklers at the top of the 3rd level. There are 5 levels of storage, which includes the storage setting on top of the racks. The in-rack sprinklers have their own valve at the riser. It is a Class II commodity to 30'. The original design was done years ago and my question is not about the original design. In a single portion of the cooler the owner is taking a 32' section of the existing racking out and installing new racking. The new racking will have the same amount of levels. The bottom 3 levels will have a "cooling cell," one on each level. I have never heard of a cooling cell on a rack like this. Not sure what the cooling cell is made of. Does a cooling cell increase the protection level from Class II? If so, how much would it change the commodity classification? Does NFPA 13 even address something like this? My assumption is that it will increase the hazard and call for greater level of protection. I have asked for the data sheet for the cooling cell and hope that it gives direction for fire sprinkler coverage. I have attached a picture, which really doesn't give a lot of information. Has anyone run into this before? Thank you! Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe My jurisdiction (I am the AHJ) has had several buildings built with private hydrants supplying the sprinkler system where the main comes into the building, through the RPZ, feeds the sprinkler system/standpipes, and leaves the building and feeds the hydrant(s). This has always seemed counterintuitive to me, at best. I feel we are "robbing Peter to pay Paul" and have wondered if this arrangement will adequately supply the sprinkler system when we (FD) pull water from the hydrant and pump it back into the FDC.
Per our state law, private hydrants have to be "protected" with a backflow. Is this configuration code compliant, and if not, what is a solution? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe What specific criteria or code references determine whether a standpipe system is classified as 'separated' rather than 'combined'?
I've seen AHJs state that even though the sprinkler system and the standpipe have separate vertical riser assemblies (control valve, check valve, and supervision), they are fed from the same underground supply (one underground service main) and will still be considered combined. We are working on a project where the AHJ has deemed the building 'partially sprinklered,' requiring the standpipe to be upgraded from 4" to 6" (which would necessitate a pump) but only if it is a combined system. We are looking for clarification or language that supports the distinction between a combined and a separated standpipe system to explore options that may avoid the need for a pump. Additionally, does anyone have thoughts on how we might be able to keep the standpipe at 4" or explore alternative approaches to avoid the pump requirement? Thanks in advance. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe I have a dry pipe system in which all test connections have an auxiliary drain except one. That one test connection is the farthest and highest connection, which is then piped down to ground level.
At ground level, the test valve is in a heated room and drains out through the wall. That pipe was filled with water (we don't know why) right to the top of the attic, froze, and burst an elbow. Should this test connection have had an auxiliary drain where the maintenance person checking for condensate and all other test connections likely would have found the filled test connection? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe What is the NFPA Commodity Classification for fruit in plastic bins (for example, cherries, floor-stacked 20 ft. high)?
The bins are open on top with holes for drainage and are full of cherries. Do the bins make this Class I a Class IV or Group A plastic instead? Where are we with the newest clean agents?
I'm running into an interesting scenario where the discussion of the phasing out by 3M of the NOVEC 1230 agent is coming up. I mentioned the competitors to NOVEC 1230 that we're aware of - FK-5-1-12 but they are interested in the next-gen stuff because they don't want to have to redo anything in the near future. Does anyone have any experience with the Fluoro-K or any other newer, lesser used in the past but now have to look into agents? I'm aware of Victaulic's Vortex and CO₂ options, but I'm asking about chemical agents. I look forward to hearing your thoughts and experience. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe Can the Quick Response Reduction be used for an above-ceiling calculation for upright heads in an interstitial combustible space?
The combustible roof deck is approximately 13'-0 above the finish floor with a ceiling of 9'-0" below. Assuming the space from the roof deck to the ceiling is 4'-0", this allows a maximum 40% reduction. Or does the calculation need to go to the finished floor for a -3 x 13/2 + 55 for a 35.5% reduction? Which is correct? Is the ceiling, in this case, the floor with only 4'-0" elevation for applying the reduction in the interstitial space, allowing the full 40% reduction? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe Is the additional flow described by NFPA 13 27.2.4.2.5 (2019) based on the original minimum design area or the minimum area after modifications?
Say I have a light hazard system with low ceilings. The default minimum area is 1,500 sqft but is reduced to 900 per Section 19.3.3.2.3.1. The calculation on the sprinklers in that 900 sqft area results in 128 gpm total flow (not including the hose allowance). If the additional flow in 27.2.4.2.5 is based on the original 1,500 sqft, then I would need to add 22 gpm of extra flow on the main to get the minimum of 150 gpm running through the main. If the additional flow is based on the 900, then I'm already meeting the requirement of 90 gpm, and I can ignore the additional flow requirement. Similarly, we start at 1500 sqft in a dry attic system, but it needs to be increased to 2,535 sqft minimum due to the dry system and sloped ceiling. Will the minimum flow as per 27.2.4.2.5 be 150 gpm or 254 gpm? This sometimes comes up when using specialty attic sprinklers, which allow for fewer operating sprinklers in the calculation. It comes down to the definition of "minimum design area". Is this the original minimum area, or the modified minimum area? In my designs I've been defaulting to the larger of the two demands to be conservative, but what is the actual intent of this clause? I haven't found any discussions relating to the changing of the minimum design area. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe NFPA 13 is clear about a limit of 10 feet under a building before pipe needs to turn up and into a building (with exceptions for trenching).
What about pipe exposed within a basement? Is there a limit to how far an underground service can run exposed within the building before the system riser? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe Has anyone ever used a slosh damper water tank on a roof as part of the fire reserve for the building?
The project is located in NYC. If so, are there any special requirements that need to be adhered to? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe We have an exterior elevator on a two-story building, required by ADA.
The required smoke detector outside the elevator door, installed under the soffit overhang, will quickly fill with dust/dirt. Any thoughts about using a heat detector at this spot that ties into the elevator recall requirement? I am the AHJ. Thank you. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe Best Practice suggests that a single FDC supply all fire sprinkler systems in a building, so no matter which FDC the fire department pumps into, all of the systems would be supplemented.
Is there a requirement in any code (except local, village, state amendments, etc.) that requires a fire department connection to connect to all systems? Or, can each system have its own FDC, provided it's properly labeled as to what system(s) are being pressurized by that particular FDC? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe I have a requirement from a client to use K25.2 sprinklers on a building up to 50-ft in height.
The design criteria that is provided under NFPA 13 is 12 K25.2 sprinklers at 50 psi, but this criteria is not available in Chapter 13 of NFPA 13. Does anyone know where this came from, or whether it's appropriate? It's for up to a 50-ft roof for protection of cartoned, non-expanded Group A plastics. Thank you. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe I have a project for which someone else did the flow test for me. At the test hydrant, I have a static of 69 psi and a residual of 64 psi at an elevation of 238'.
According to the information I was given at the flow hydrant, I have a static of 24 psi and a pitot of 25 psi at an elevation of 308'. With a coefficient of .90, they show a flow of 839 gpm. My question is - do you think it is acceptable to use a flow test showing a pitot reading higher than the static read at the same hydrant? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe Subject: Two story convenience opening separation from corridors.
NFPA 101 (2021 edition) Section 8.6.9.1 permits convenience openings for two adjacent stories. But, these convenience openings shall be separated from corridors (requirement #3) and further states that separation should be by a smoke partition (requirement #5). How do you define a corridor versus an open floor area or lobby per NFPA 101, since no definitions are given within the code? Jurisdiction is required to follow NFPA 1 and NFPA 101. For example, a building has a large assembly space on the second floor. All doors from the assembly space lead to a ~40'-0" wide circulation space (+200'-0" long in the other direction). To reach the building exit stair, occupants from the assembly room must traverse the 40'-0" wide circulation space. Within this circulation space is a ~20'-0" x 40'-0" vertical opening that connects the 1st and 2nd floor. Should this circulation space be considered a corridor, and should the vertical opening be prohibited from being classified as a convenience opening without a smoke partition separating from the corridor? Or is the 2nd floor space to be considered an open floor area, with exits immediately accessible in different directions (NFPA 101 7.5.1.1.1) and not consider it a corridor? The width of the circulation space seems too wide to be defined as a corridor but NFPA only provides minimum width requirements for corridors, and no maximum width for a space to be considered a corridor as far as I can determine. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe If the fire sprinklers for an entire area or building have to be replaced, such as if they are more than 50 years old, is there any problem or benefit (hydraulically) from increasing the replacement sprinklers to the next higher K-factor (e.g., K5.6 to K8.0 or K8.0 to K11.2), especially for production and storage areas?
Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe Forward Flow Test Confusion... I have an NFPA 13R system built in 2013 that doesn't have any hose connection(s) for forward flow testing. The sprinkler contractor is saying they're unable to conduct the test.
I am attempting to understand the codes around this topic and ran into several questions. First, NFPA 25: 2020 NFPA 25 13.7.2.3 states, "Where connections do not permit verification of the forward flow test at the minimum flow rate of system demand, tests shall be conducted at the maximum flow rate possible." Can someone please explain what this means exactly? My second question concerns using the main drain to conduct the forward flow test if it's sized appropriately. A previous Meyer Fire blog post, "Solutions for the Overlooked Forward Flow Test," Option 4, mentioned the 2016 NFPA 13 A8.16.2.4.2, but I cannot find that section in the 2019 version. Has this method changed somehow? Can the sprinkler contractor use the main drain as a means to conduct the forward flow test? If so, what else does the AHJ need to know? Calcs to prove drain size can flow system demand? Pitot reading? Thank you for reading and I'd love to find some clarity. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop Feb '25 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
March 2025
PE PREP SERIES |