MeyerFire
  • Blog
  • Forum
  • TOOLKIT
    • ALL TOOLS
    • BUY THE TOOLKIT
  • UNIVERSITY
    • ALL COURSES
    • JOIN THE UNIVERSITY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE PREP SERIES
    • PE Old Questions
  • STUDENTS
    • LAND JOB/INTERNSHIPS
    • STUDENT CONNECTOR
  • LOGIN
    • TOOLKIT-ONLY LOGIN
    • UNIVERSITY LOGIN
  • STORE
  • OUR CAUSE
    • ABOUT MEYERFIRE
    • JOB OPENINGS
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT
Picture

When Does Phantom Flow Requirement Apply?

12/8/2023

13 Comments

 
NFPA 13, 2022 Edition, Sections 28.2.4.2.4 says to that a design area can be only the sprinklers within the available design area whenever the available floor area is less than the density/area size.

The next section, Section 28.2.4.2.5, says that when the total flow is less than the density x minimum design area, an additional flow (phantom flow) shall be added at the common point of connection.

When do you apply one versus the other?

If I am interpreting this correctly, you only apply the 28.2.4.2.5 when you have the available floor area, but not the minimum flow?

​​​​​​​​​​​​​​​​​​​​​​​​​Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
13 Comments
Pete H
12/8/2023 07:20:23 am

I think I'm having this conversation elsewhere and it's honestly making me think this is a conflict specific to NFPA 13 (2022 edition).

Cause the corresponding section in 2016 goes like this:

23.4.4.2.4* Where the available floor area for a specific area/design criteria, including any extension of area as required by 11.1.2 and Section 12.3, is less than the required minimum design area, the design area shall be permitted to only include those sprinklers within the available design area.

23.4.4.2.5 Where the total design discharge from these operating sprinklers is less than the minimum required discharge determined by multiplying the required density times the minimum required design area, an additional flow shall be added at the point of connection FURTHEST [please the caps cause this is what this post is about] from the source to increase the overall demand, not including hose stream allowance, to the minimum required discharge.

A.23.4.4.2.4 outlines the procedure for this calculation.

---

Now in 2022 we have the section read as follows:


28.2.4.2.4* Where the available floor area for a specific area/density design criteria, including any extension of area as required by 19.1.2 and Section 20.13, is less than the required minimum design area, the design area shall be permitted to only include those sprinklers within the available design area.

[and the annex section details the procedure for doing this where you are still adding the additional flow at the point of connection FURTHEST from the source. A.28.2.4.2.4 (4) ]

28.2.4.2.5* Where the total design discharge from the operating sprinklers is less than the minimum required discharge determined by multiplying the required design density times the required minimum design area, an additional flow shall be added at the point of common connection CLOSEST to the source to increase the overall demand, not including hose stream allowance, to the minimum required discharge.

[ The Annex for this section refers you to a figure... which still shows a point to add this flow... that sadly works as closest to the remote area/furthest from the source... but also closest to the source, because it's not a very complex figure ].

Anyone else's insight is welcome.

But I'd stick with 2016's rules and the Annex of 28.2.4.2.4 and go with the connection point furthest from the source (or nearest to the remote area you're calculating) as where to add the required additional flow.

I think if you have some miracle 900 square foot design area reduction calc that comes up with less than 150 gpm of flow (not counting hose) in light hazard, since you're not technically in 28.2.4.2.4 you can use the "closest to source" point for the additional flow, but if you're in 28.2.4.2.4, you still should apply the more stringent demand, which will be adding that flow at the connection point furthest from source/closest to your remote area.

I hope I made this make some sense.

Reply
Dan Wilder
12/8/2023 08:18:32 am

Had to look up why the original change but here is the substantiation. I believe the interpretation was being applied to the far end of systems and not related to the actual tie-in point of the system being applied with the additional flow requirements (so off page to the right of Figure A referenced in 28.2.4.2.5) so it was proposed to change in the 1st draft of the 2022 edition, then discussed in E&S and other venues as to where it should be applied (on the end of the main feeding the area, the connection point of the feed main to another feed main, the remote end of the full system regardless of the actual tie in point for the area being calculated, I think even dividing the flow by the number of branch lines and adding that in at each point came up). Ultimately, the POC from the smaller system to the building system "proper" was passed in Public Comment No. 258-NFPA 13-2020 [Section No. 28.2.4.2.5] as to allow the system main feeding the smaller main the ability to support the larger area being calculated under the "Phantom Flow" addition.

Resolution: FR-1315-NFPA 13-2019
Statement: The current wording contradicts itself. The text states additional flow is being added at the point of connection of the branch line to the cross main. After that, it states to go the furthest from the source to add the additional flow. The point of connection would be closer to the source if it is the branch line connecting to the cross main, not further away.

Reply
Pete H
12/8/2023 08:33:51 am

Yeah.... I feel like a lot of headaches could have been avoided if they just changed the words to the connection point on the main closest to the calculated area.

But, this stuff is decided by smarter heads than mine.

Dan Wilder
12/8/2023 07:35:04 am

Rereading things again...the light came on this morning as this is an OR statement but, as always, feel free to correct me...it's still early in the day. I've been lucky and not had to utilize it much other than some canopies.

To answer your question, this isn't a choose one, these are complimentary.

NFPA requires the remote area to be sized per the hazard (1500 for Light/OH1/OH2, 2500 for EH1/EH2, 2000 or 2500 for storage...all dependent on allowances like QR, high temp, larger K-Factor. If the higher hazard area being covered is smaller than the minimum required, there are 2 choices.

1-Calulate the higher hazard area
1a*-With the 15' extension of the higher density if there are no barriers, draft curtains, or elevation changes AND the additional area of the lower density to meet the minimum.
1b*-Without the 15' extension but still providing the total required area with the addition of the lower density area.

2-Calculate the higher density area (with or without the extension based on the construction)
2a-Use Phantom Flow to identify the shortage in total water demand from required Density x Area vs. the actual water demand. Then add that shortfall as required.

*Allowance per 19.1.2(1)(2)(3) and 20.13.1 (1)(2)(3)

28.2.4.2.4 is providing guidance to calculate using an alternate calculation method to the full area by using "phantom flow". 28.2.4.2.5 is providing guidance on where to apply the previous section's shortfall (Appendix Section (4) below)

The appendix has some additional commentary:

The following steps outline the procedure for calculation in accordance with 28.2.4.2.4:
(1) Calculate the hydraulic design discharge including those sprinklers within the available floor area.

(2) Calculate the minimum required discharge by multiplying the required design density times the required minimum design area.

(3) Subtract the discharge calculated in Step 1 from the discharge calculate in Step 2.

(4) Where the discharge calculated in Step 3 is greater than 0, the hydraulic design discharge is recalculated including an additional flow equal to that calculated in Step 3. The additional flow is added at the point of connection of the branch line to the cross main furthest from the source.

(5) Where the discharge calculated in Step 3 is less than or equal to 0, the hydraulic design discharge is as calculated in Step 1.


A good write up below:
https://pdfcoffee.com/phantom-flow-pdf-free.html

Reply
Eric R
12/8/2023 09:22:41 am

Dan,

You've got this down pretty good here.

I'll just reiterate that the designer does have a choice here, and that phantom flow is not always required to be used if the designer follows the adjacent hazards remote area rules.

In some cases you'll get a more efficient pipe system using the phantom flow approach, but other times you can save significant waterflow overall by using the larger design area approach of Dan's option 1 and controlling your densities via tighter head spacing in the more demanding area to balance your individual head discharge pressures so the heads in the lower hazard area aren't over-discharging.

I'll caveat this by saying a strict following of the adjacent hazard rules can create some theoretically sketchy protection schemes, especially if you mix in QR area reduction to the lesser hazard, so a bit of good judgement should probably be applied.

I personally prefer to use the adjacent hazards with the full size remote area most of the time nowadays, simply because it is easier to present on drawings/calc where you can show the actual densities on a head by head basis and just note which ones are in the higher hazard portion(at least in AutoSprink).

Reply
sean
12/31/2023 11:12:25 pm

the adjacent hazard option only works when the resulting flow is equal to or greater than density * area

Dave
12/8/2023 11:35:31 am

Yep, and the 2019 Handbook commentary says these sections "were added in 2013 to provide an alternative...as opposed to having to calculate a full design area....in response to concerns with calculation areas that crossed boundaries between hazard areas sometimes containing sprinklers having different orifice size.

[NOT sprinkler heads ;-) ]

Reply
sean
12/31/2023 11:13:14 pm

i think this was added to add clarity as some were treating it two different ways

Alex
12/8/2023 08:46:31 am

This has happened multiple times now where I am going to be submitting a drawing and this forum makes a post that has me changing my design! Thank you for whoever posted the original comment and everyone's feedback. This has caused me to increase my main to a second floor awning.

Reply
Nick
12/8/2023 08:59:06 am

To be honest, I have yet to apply this rule but my understanding is that you would in way need to apply both rules and adjust based on the result of your calculations.

I believe that you could only ever apply 28.2.4.2.5 if you are following 28.2.4.2.4, since assuming your actual design area is meets the minimum area requirement, your actual flow would never be less than your "minimum required discharge" (if you were doing things correctly).
 
You would first run the calculation with the full floor area (in this case less than your minimum design area) and see what waterflow is required. Due to overdischarge and other inefficiencies, you might be flowing close to the "minimum required discharge" defined as the density multiplied by the "minimum design area". Any differences between the actual system flow and the minimum required discharge need to be made up through the phantom flow.

There could technically be a situation where actual design area is smaller than the minimum required area, but the actual flow is as much or more than the minimum required discharge (as defined in 28.2.4.2.5).

That is my interpretation of the two sections.

Reply
sean
12/31/2023 11:14:14 pm

my example that this comes up is spray booths

Reply
Dave
12/8/2023 11:24:20 am

In this Reliable webinar about changes to the 2022 edition of NFPA 13, Cary talks about the change / correction of the point o connection at about 1:18:30. The whole thing is worth a listen.
https://youtu.be/NniMHPokyMQ?si=yMkR_bMUPTFS0eGe

Reply
Thomas
2/19/2024 08:46:30 am

Would 2022 edition of NFPA 13; 28.2.4.2.5 apply to a very small outside loading dock?

I have a 1,437ft² loading dock with a dry system. The design area includes (12) heads and 130ft² coverage per head. Per UFC design requirements, my design perimeters are .2 over 3,500ft². Would I be required to provide a total design discharge of 700 GPM for this tiny system?

I don't think room design method can be applied since I doubt the overhead doors are considered automatic or self-closing. Plus, NFPA 13; 19.2.3.3.5 references "interior walls" and nothing on exterior.

Reply



Leave a Reply.

    SUBMIT A QUESTION
    Picture
    Why Sponsor?

    ALL-ACCESS

    Picture
    GET ALL OUR TOOLS

    SUBSCRIBE

    Subscribe and learn something new each day:
    I'm Interested In:

    COMMUNITY

    Top May '26 Contributors
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    SEE LEADERBOARD

    YOUR POST

    SUBMIT A QUESTION

    PE EXAM

    Get 100 Days of Free Sample Questions right to you!
    SIGN ME UP!

    FILTERS

    All
    A1171
    ABA
    ADA
    ASCE 7
    ASME A17.1
    ASTM E1354
    Blog Thread
    Daily Discussion
    Design-documents
    EN 12259-1
    EN 12845
    Explosion Protection
    Explosion-protection-prevention
    Fire Detection And Alarm Systems
    Fire Dynamics
    Flammable And Combustible Liquids
    Flammable-combustible-liquids
    FM Global
    Human-behavior
    IBC
    ICC 500
    IEBC
    IFC
    IMC
    IPC
    IRC
    ISO
    Means Of Egress
    NBC
    NFPA 1
    NFPA 10
    NFPA 101
    NFPA 11
    NFPA 110
    NFPA 1142
    NFPA 1221
    NFPA 13
    NFPA 13D
    NFPA 13R
    NFPA 14
    NFPA 15
    NFPA 16
    NFPA 17A
    NFPA 20
    NFPA 2001
    NFPA 214
    NFPA 22
    NFPA 220
    NFPA 24
    NFPA 241
    NFPA 25
    NFPA 291
    NFPA 30
    NFPA 307
    NFPA 30B
    NFPA 31
    NFPA 33
    NFPA 37
    NFPA 400
    Nfpa-409
    Nfpa-415
    Nfpa-45
    Nfpa-495
    NFPA 497
    NFPA 5000
    NFPA 502
    NFPA 54
    NFPA 55
    NFPA 654
    NFPA 68
    NFPA 70
    NFPA 701
    NFPA 72
    NFPA 75
    NFPA 770
    NFPA 82
    NFPA 850
    NFPA 855
    NFPA 90A
    NFPA 92
    NFPA 96
    NICET
    OBC
    OSHA
    Passive Building Systems
    PE Prep Guide
    PE Prep Series
    PE Sample Problems
    Poll
    Smoke Management
    Special Hazard Systems
    UFC 3-600-01
    UFC 3-601-02
    UFC 4-021-01
    UFC 4-211-01
    UPC
    Updates
    Water Based Fire Suppression
    Weekly Exams


    ARCHIVES

    June 2026
    May 2026
    April 2026
    March 2026
    February 2026
    January 2026
    December 2025
    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    November 2016
    October 2016
    July 2016
    June 2016


    PE PREP SERIES

    SEE LEADERBOARD

    SEARCH THE FORUM

    RSS Feed

Picture
​Home
Our Cause
The Blog
The Forum
PE Exam Prep
The Toolkit

MeyerFire University
​Pricing
Login
​Support
Contact Us
Picture

MeyerFire.com is a startup community built to help fire protection professionals shine.
Our goal is to improve fire protection practices worldwide. We promote the industry by creating helpful tools and resources, and by bringing together industry professionals to share their expertise.

​MeyerFire, LLC is a NICET Recognized Training Provider and International Code Council Preferred Education Provider.

All text, images, and media ​Copyright © 2016-2025 MeyerFire, LLC

We respect your privacy and personal data. See our Privacy Policy and Terms of Service. 
The views, opinions, and information found on this site represent solely the author and do not represent the opinions of any other party, nor does the presented material assume responsibility for its use. Fire protection and life safety systems constitute a critical component for public health and safety and you should consult with a licensed professional for proper design and code adherence.

Discussions are solely for the purpose of peer review and the exchange of ideas. All comments are reviewed. Comments which do not contribute, are not relevant, are spam, or are disrespectful in nature may be removed. Information presented and opinions expressed should not be relied upon as a replacement for consulting services. Some (not all) outbound links on this website, such as Amazon links, are affiliate-based where we receive a small commission for orders placed elsewhere.

  • Blog
  • Forum
  • TOOLKIT
    • ALL TOOLS
    • BUY THE TOOLKIT
  • UNIVERSITY
    • ALL COURSES
    • JOIN THE UNIVERSITY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE PREP SERIES
    • PE Old Questions
  • STUDENTS
    • LAND JOB/INTERNSHIPS
    • STUDENT CONNECTOR
  • LOGIN
    • TOOLKIT-ONLY LOGIN
    • UNIVERSITY LOGIN
  • STORE
  • OUR CAUSE
    • ABOUT MEYERFIRE
    • JOB OPENINGS
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT