With all our submittals we are required to have a PE review and stamp before submitting to the AHJ.
Has anyone else wondered why it takes two business weeks to get review and approval? I appreciate the statement that they are being reviewed for quality control yet when I've found errors with approved city drawings and they have no responsibility. Any opinions? Anyone seeing "pay the fee" and getting immediate AHJ approval? Posted anonymously for discussion. Discuss This | Submit Your Question | Subscribe
6 Comments
9/23/2019 10:28:45 am
For many of the AHJs I work with, the job is pulling long days and barely keeping up with the workload. I have not seen many that are over-staffed. My experience is that two weeks is a very common minimum review period.
Reply
K
9/23/2019 10:46:50 am
I’ve been fortunate to be involved with the plan review process for multiple jurisdictions. I would challenge the “they have no responsibility” statement. Inspectors and reviewers can go to jail for negligence just as easily as an engineer or designer can. A lot of times these review offices are integrated right in with the fire department and are the first people the operations personnel turn to. If nothing else, they have a responsibility to ensure operations (or suppression) personnel can do their job. Further, the general public and media turn to the permitting office for a lot of information if something were to go wrong.
Reply
Johnathan H
9/23/2019 11:20:10 am
As an AHJ, that was perfectly said! Sadly, in our little town of 18,000 I do the work of the Building official AMD the Fire Marshal, So I am looking at plans all day long. Fortunately I have a contract inspector that is knowledgeable enough and experienced enough to do a great job in the field! Where he doesn't know, he is not afraid to ask, plus about half of the submitting contractors around here are extremely good and conscientious in both their plan prep, as well as their installs!
Reply
Matthew King
9/23/2019 10:58:04 am
Where I am at 2 days would be a godsend. Currently, 2- 3 months with an expediter depending on content. Without up to 6 mo backlog. They are very short handed here. They are converting to electronic submittal process.
Reply
Scott Thomas
9/23/2019 08:51:58 pm
As an AHJ (fire), I'm glad you asked. I'm always happy to educate contractors, design professionals, the public, local and state politicians why certain tasks are not completed in the fashion that suits every individual needs. As David J Branson and K explained AHJ's are understaffed and working in a world where everyone's project trumps all others. As most Fire Officials we strive to complete our job tasks with integrity in a timely fashion. Here are a few responsibilities that most Fire Officials have:
Reply
Mike
9/23/2019 09:36:08 pm
I think the main issue is that fire sprinklers usually are contracted very late in the building process. Sometimes the building is already being built. The contractor then has to design, submit and get approval for a prefabricated project and can be the last to install. I install anyways and have never had to change piping because of errors in design.
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop November '24 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
December 2024
PE PREP SERIES |