MeyerFire
  • Blog
  • Daily
  • Exam Prep
    • CFPS Tools
    • NICET Tools
    • PE Forum & Errata
    • PE Problems
    • PE Store
    • PE Tools
    • PE Prep Series
  • TOOLS
    • TOOLKIT (FREE TRIAL)
    • *TOOLKIT (PURCHASE)
    • SUBMIT AN IDEA
    • BACKFLOW DATABASE*
    • CLEAN AGENT ESTIMATOR
    • CLOUD CEILING CALCULATOR
    • DOMESTIC DEMAND
    • FIRE PUMP ANALYZER
    • FIRE PUMP DATABASE*
    • FIRE FLOW CALCULATOR*
    • FRICTION LOSS CALCULATOR
    • HANGER SPACER
    • IBC TRANSLATOR*
    • K-FACTOR SELECTOR
    • NFPA 13 EDITION TRANSLATOR ('19 ONLY)
    • NFPA 13 EDITION TRANSLATOR ('99-'19)*
    • LIQUIDS ANALYZER*
    • OBSTRUCTION CALCULATOR
    • OBSTRUCTIONS AGAINST WALL*
    • PLUMBING FIXTURE COUNTS
    • REMOTE AREA ANALYZER
    • QUICK RESPONSE AREA REDUCTION
    • SPRINKLER DATABASE*
    • SPRINKLER FLOW*
    • TEST & DRAIN CALCULATOR
    • THRUST BLOCK CALCULATOR
    • TRAPEZE CALCULATOR
    • UNIT CONVERTER
    • VOLUME & COMPRESSOR CALCULATOR
    • WATER SUPPLY (US)
    • WATER SUPPLY (METRIC)
  • TOOLKIT
  • LOGIN
  • STORE
  • About
Picture
A FORUM FOR FIRE PROTECTION QUESTIONS & PE EXAM PROBLEMS | SUBSCRIBE NOW

Hydraulic Calculations Required for Each Zone?

7/24/2020

13 Comments

 
I need an answer for a simple question. I am working on a large airport project expansion. I have a structure of 4 levels with 70+ sprinkler zones.

Is there an NFPA standard requirement stating that each area requires a hydraulic calculation on each system?

Each system is not prototypical.

​​​​​​​Submitted anonymously and posted for discussion. Discuss This | Submit Your Question | Subscribe
13 Comments
Glenn Berger
7/24/2020 10:13:14 am

Since each system is not identical, separate calculations would be required.

Are you trying to size piping identically? Are the spaces the same hazard categories?

Reply
Jessica L.
7/24/2020 10:42:00 am

An experienced sprinkler plan reviewer should be ok with you submitting one calc per hazard/sprinkler k-factor/system type/pipe size arrangement. ****Be sure you have the knowledge and experienced to make this judgement, and defend it!

Also, check with the airports' submittal requirements...some airports are managed by various parties, with unique requirements specific to each airport...they could possibly required a calc for each zone, or have other special requirements that go beyond NFPA 13.

Reply
Ivonn
7/24/2020 11:06:19 am

I dont have a simple answer maybe no, are there 70 zones or 70 systems?, all zones have the same hazard? What are the most critical pipe configuration?, What is the critical path? What is the most remote or high vs the supply? You need to consider that questions and make a decision

For example in the 4th floor have 3 zones but the farest from supply its a light hazard and the nearest its an extra hazard, the two in a tree pipe configuration, personaly I will calculate the extra hazard or if the farest part is a grid system and the nearest is a tree, tree its more "critical" but I want to choose the lower diameter possible so I will calculated both.

If you have multiple ocupancies (LH,OH,EH) and multiple pipe configurations (Grid, tree, loop), maybe you need to do several hydraulic calculations, but maybe no 70+

Also you need to consider what the AHJ required, NFPA 13 Ed. 2019 do not required one hydraulic calculation per "zone" or per "level" as far as I know.

Reply
CJ Bonczyk
7/24/2020 11:42:42 am

If the systems are not entirely identical in layout I strongly recommend doing the calculations to indicate the hydraulic capability of each zone. For instance if a remodel happens within an area on a specific floor there is no way in determining the hydraulic capability of the system installed. Occupancy changes, building remodels or MIC issues, can alter system capability within a year or two. If something happens from a legal standpoint you have documentation to fall back on on how the system area was protected and why. These placards are usually required on each by the fire marshal anyway. NFPA 13 2019 Handbook Section 28.5 gives a clearer reason why these should be placed on each system.

The only time in which I have used the same hydraulic placard for corresponding floors is if I had an exact layout for multiple floors and I calculated the highest floor and used the same hydraulic plate for the lower floors and denoted on the lower floor placards that the information was based on the hydraulic capability/demand of the highest floor.


Also as Jessica stated earlier confirm with the airport that there is no insurance carrier that will require calculations for all systems.

Reply
Jesse
7/24/2020 12:43:40 pm

If by zone you mean system, then yep, each system needs to be proven. Its most acceptable proving the end-head back to the residual hydrant as opposed just to base of riser so even if each system were identical, the distance from BOR to residual hydrant would be different. If its a single system with multiple zones, the most hydraulically remote would be all that's needed but be prepared to defend your logic. And totally agree with a previous comment about proving multiple areas in case of a future remodel. I rarely sign a drawing with only one area calc'd unless it's very small for that very reason.

Reply
Franck
7/24/2020 03:20:22 pm

Working for an insurance company, I can confirm what has been said.
As a minimum, one hydraulic calculation per different system (as all results might be slightly different, and we are looking for « actual design ».
In addition, if different hazards/configuration on one system, we may ask several calculations to be sure that all configurations are adequately covered.
This is particularly true for EH occupancies or for different storage commodities/arrangement

Reply
Jimmy Landmesser, Jr.
7/24/2020 04:44:17 pm

So, first what you mean by "zone" would need to be understood.
As stated above, there are two main reasons that a single building requires multiple design calculations- 1) multiple systems serving said building or 2) when you there are different design bases (also called occupancy hazards) present. As others have said, only a single design calculation is required for the most remote area of a single system or design basis, even if multiple floors are fed from a single system. Each floor will normally have a zone control valve. On the other, there are sometimes different "zones" on a single floor that each have a different design basis. For example, a building that has offices that are light hazard, an automotive garage of ordinary hazard and high rack storage that is an extra hazard occupancy. Though a single system of a one-story building, each of these areas will require an independent design calculation.

As for reference, per NFPA 13 (2019)- 19.2.3, "the total system supply requirements for each design basis shall be determined in accordance with the procedures of Section 27.2 unless modified by a section of Chapter 19 or Chapter 20.".

Reply
Max
7/24/2020 05:07:39 pm

I would ask for one remote area calculation per riser at a minimum.

Reply
Mike
7/24/2020 07:52:03 pm

Considering the simplicity of today's CAD systems, it's relatively easy to calc many areas in a short amount of time. I'd do a detailed analysis of your different systems. If you use area reduction in some areas but not others, I wouldn't expect those designs to be used in areas where area reduction isn't a factor.

Reply
SK
7/25/2020 03:47:24 am

The basic of all calculations are there to demonstrate your decision against Code/AHJ and justify your design, in this case is NFPA 13. There is no hard and fast rule for this. This is just subjective. So i would suggest performs as much as cals to covers as below;

-Demonstrate you get water with adequate pressure at FARTHEST location
-LARGEST DEMAND Area (Consider Occupancies w.r.t. levels/zones)
-WORST Case, which will decide your system sizes at the end.

So based on my limited knowledge about Airport structure, probably 12-15 calculation for difference Occupancies/Area should serve the purpose but certainly not 70+....

Reply
koray uluc link
7/26/2020 05:18:54 am

According to NFPA 13 if you design systems with hydraulic calculation method then you should run a calculation for all of them according to NFPA13 27.2.4.1
Sometimes AHJ may ask (in my point of view, should ask) for additional calculations to be sure that designer did choose actual "most demanding area"(NFPA13 A.27.2.4.7).
Don't forget that sloped ceilings and grid type piping makes hard to find the most demanding area at first attempt.

Reply
Hassan
10/23/2020 05:06:43 am

I have Grid Network of piping with extra hazard. The area is covered by 1800 Sprinklers, normally distributed through out the space with the 9 sqm/sprinkler. in order to select the size of the pump what is the criteria to decide the number of sprinklers that will be operating together in order to verify the water flow rate.

Reply
Hassan
10/26/2020 09:28:19 am

Thanks for your valuable feedback really appreciated.
I truly have four ZCVs each of them cover separate zone with 450 Sprinklers
in order to run my hydraulic test how many Sprinkles in the critical path will be included in my calculations our of 450 connected to the ZCV this figure will lead me to decide the GPM for the pump and accordingly to decide head.

Reply



Leave a Reply.

    Jump to: Daily Posts
    Jump to: PE Problems
    Picture
    Why Sponsor?

    Free Signup

    Subscribe and learn something new each day:
    I'm Interested In:

    Community

    Thank You to Our Top
    ​January '21 Contributors!
    1. Franck
    2. CJ B.
    3. Dan W.
    4. Jesse
    ​5. Gleen B.
    6. Casey M.
    7. Mike
    8. Pete
    9. HJ
    10. Wayne


    Your Post

    SUBMIT A QUESTION

    The Toolkit

    Sprinkler Designer or Engineer?
    ​
    ​Get all of our tools, including the Sprinkler Database, Friction Loss Calculator, Fire Pump Analyzer and more:
    Picture
    FREE 30-DAY TRIAL
    GET THE TOOLKIT

    Filters

    All
    ABA
    ADA
    ASCE 7
    ASME A17.1
    Daily Discussion
    Design Documents
    Explosion Protection & Prevention
    Fire Detection And Alarm Systems
    Fire Dynamics
    Flammable & Combustible LIquids
    FM Global
    Human Behavior
    IBC
    IFC
    Information Sources For Analysis
    IRC
    Means Of Egress
    NFPA 1
    NFPA 10
    NFPA 101
    NFPA 11
    NFPA 110
    NFPA 12
    NFPA 13
    NFPA 13D
    NFPA 13R
    NFPA 14
    NFPA 15
    NFPA 17A
    NFPA 20
    NFPA 2001
    NFPA 214
    NFPA 22
    NFPA 24
    NFPA 25
    NFPA 291
    NFPA 30
    NFPA 33
    NFPA 400
    NFPA 415
    NFPA 497
    NFPA 5000
    NFPA 502
    NFPA 54
    NFPA 55
    NFPA 654
    NFPA 68
    NFPA 70
    NFPA 72
    NFPA 92
    NICET
    Passive Building Systems
    PE Prep Guide
    PE Prep Series
    PE Sample Problems
    Poll
    Smoke Management Systems
    Special Hazard Systems
    Types Of Analysis
    UFC 3 600 01
    UFC 3-600-01
    Updates
    Water Based Fire Suppression
    Weekly Exams


    Archives

    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    November 2016
    October 2016
    July 2016
    June 2016
    June 2015


    Daily
    Daily discussions are open-ended fire protection, fire alarm, and life safety questions submitted anonymously for the benefit of sharing expertise and learning from other perspectives. Anyone can submit a question here:
    SUBMIT A QUESTION

    Exam Prep

    Picture
    2020 PE Prep Guide​
    ​(Available Now!)
    Picture
    PE Prep Series
    ​(Available Now!)
    2020 PE Prep Series
    Current Leaderboard
    ​(Click to enlarge)
    Fire Protection PE Exam Prep

    PE Problems
    ​Visit July-October for daily Fire Protection PE Exam sample questions.

    Solutions are posted the day after posting.

    Comment with your solutions, questions or clarifications.

    Please note that questions posted are unofficial and in accordance with NCEES rules are intended to be similar to actual exam questions, not actual exam questions themselves.

    RSS Feed

Home - About - Blog - Contact - Exam Prep - Store
Picture
Copyright © 2020 MeyerFire, LLC
The views, opinions, and information found on this site represent solely the author shown and do not represent the opinions of any other party, nor does the presented material assume responsibility for its use. Fire protection and life safety systems constitute a critical component for public health and safety and you should consult with a licensed professional for proper design and code adherence. Some (not all) outbound links on this website, such as Amazon links, are affiliate-based where we receive a commission for orders placed elsewhere.
  • Blog
  • Daily
  • Exam Prep
    • CFPS Tools
    • NICET Tools
    • PE Forum & Errata
    • PE Problems
    • PE Store
    • PE Tools
    • PE Prep Series
  • TOOLS
    • TOOLKIT (FREE TRIAL)
    • *TOOLKIT (PURCHASE)
    • SUBMIT AN IDEA
    • BACKFLOW DATABASE*
    • CLEAN AGENT ESTIMATOR
    • CLOUD CEILING CALCULATOR
    • DOMESTIC DEMAND
    • FIRE PUMP ANALYZER
    • FIRE PUMP DATABASE*
    • FIRE FLOW CALCULATOR*
    • FRICTION LOSS CALCULATOR
    • HANGER SPACER
    • IBC TRANSLATOR*
    • K-FACTOR SELECTOR
    • NFPA 13 EDITION TRANSLATOR ('19 ONLY)
    • NFPA 13 EDITION TRANSLATOR ('99-'19)*
    • LIQUIDS ANALYZER*
    • OBSTRUCTION CALCULATOR
    • OBSTRUCTIONS AGAINST WALL*
    • PLUMBING FIXTURE COUNTS
    • REMOTE AREA ANALYZER
    • QUICK RESPONSE AREA REDUCTION
    • SPRINKLER DATABASE*
    • SPRINKLER FLOW*
    • TEST & DRAIN CALCULATOR
    • THRUST BLOCK CALCULATOR
    • TRAPEZE CALCULATOR
    • UNIT CONVERTER
    • VOLUME & COMPRESSOR CALCULATOR
    • WATER SUPPLY (US)
    • WATER SUPPLY (METRIC)
  • TOOLKIT
  • LOGIN
  • STORE
  • About