In a strict "like-for-like" repair, are hydraulic calculations required?
Is there a code basis either way? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
14 Comments
James Phifer
7/6/2022 08:08:53 am
If it's like for like, then nothing has changed and the calculations should be fine. Must be like for like though. Same k-factor or same friction loss characteristics, same equivalent length.
Reply
Jesse
7/6/2022 08:12:22 am
That is entirely an AHJ question, and AHJs in my area differ. For most, no. But a few want updated hydraulic calculations to assess how any degradation in the latent water supply may affect design density.
Reply
Peter
7/6/2022 08:13:56 am
No. Provided that legacy system didn't use specially listed sprinklers.
Reply
JI
7/6/2022 08:23:29 am
Like for like may be okay in some circumstances, however the code does change. If an old sprinkler system is to be completely redone from the alarm valve or whatever the scope of work happens to be, then everything upstream may require an upgrade. Generally work of this scope will require a permit, and the AHJ will dictate what is to be done. For example, the AHJ may want the system to be updated to current code if the existing system is not up to standards.
Reply
Dan Wilder
7/6/2022 08:32:26 am
13 19' Edition for Existing System Modifications
Reply
Glenn Berger
7/6/2022 08:34:18 am
The above is a very good discussion on this subject. Just curious, why is there going to be a "like for like" repair being preformed?
Reply
Adam Jensen
7/6/2022 10:34:37 am
I posed the question.
Reply
Glenn Berger
7/7/2022 08:14:36 am
Recommend getting a water analysis preformed. What is the source of the water supplied to the site?
You as the designer will have to decide if you are comfortable with the changes you are making - comfortable that they are not affecting the original design; pipe is the same, elevations are the same, drops are the same (flex versus hard-pipe), sprinkler heads are still flowing the same GPM as originally calculated, fittings, etc.
Reply
Anthony
7/6/2022 08:47:02 am
In a like for like replacement 'most' code treats it as a repair and leaves it alone.
Reply
sean
7/8/2022 09:13:53 pm
One question would be from the AHJ what proof does the existing system is in compliance. Could the original be pipe schedule? Were modifications made from the original design?
Reply
AHJ
7/9/2022 06:22:20 am
As an AHJ and FPE (Go Terps!), I require a scope of work letter that states the nature of the repair/replacement. In most cases, a like for like will not trigger a plans review. I also have field inspectors that usually visit the work site to view the progress and scope of work. If in his judgement, the work goes beyond the original scope, then a work stop order is issued and a formal plans review will be required in order to continue.
Reply
Alex
7/9/2022 09:50:45 pm
Hi,
Reply
6/20/2023 02:01:23 pm
Great blog post! I appreciate your insightful perspective on fire repair. If you're interested, we have a site that offers valuable information on hydraulic calculations for such repairs. We'd love to hear your thoughts!
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop November '24 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
January 2025
PE PREP SERIES |