MeyerFire
  • Blog
  • Forum
  • TOOLKIT
    • ALL TOOLS
    • BUY THE TOOLKIT
  • UNIVERSITY
    • ALL COURSES
    • JOIN THE UNIVERSITY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE PREP SERIES
    • PE 100-Day Marathon
  • LOGIN
    • TOOLKIT-ONLY LOGIN
    • UNIVERSITY LOGIN
  • STORE
  • OUR CAUSE
    • ABOUT MEYERFIRE
    • JOB OPENINGS
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT
Picture

How to Address Water Supply w/ Replacements?

8/10/2023

9 Comments

 
How do I, as an AHJ, address contractor scope limitations?

Project where an installer presents plans to replace 328 sprinklers and is changing some pipes out. Many times the installer says they're only responsible for pipe from the riser - not for a hydrant flow tests. 

What is the best way to navigate this to be sure that there's still sufficient water available?

It could be a one-for-one replacement, but what if there's significant work being done - what code basis is there to make sure than an effectively-new system can work with today's water supply?

Thanks in advance.

​​​​​​​​​​​​​​​​​​​​​​​​Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
9 Comments
Pete H
8/10/2023 07:30:04 am

While their contract may only be responsible for pipe to riser, they still would have to calculate a sufficient modification to a system (as in: not a 1:1 relocate or a reduction in hazard or demand.)

As per NFPA 13 (2016) 8.15.20.5 there are very specific rules demanding hydraulic calculations for sprinkler system modifications. Basically if they added heads (went beyond 1:1 relocate) or did multiple heads off outlets, or changed the design in another sufficient manner (use of Flexheads) as the AHJ, you are in your rights to say "I want you to prove the system can work hydraulically."

And then they'll need a flow test to calculate the system by. If their contract does not have a provision to provide/facilitate a flow test and provide calculations, they need to charge their client an extra. But that's nothing to do with the AHJ.

Reply
Alex
8/10/2023 07:33:09 am

When you replace or relocate sprinklers, you must provide hydraulic calculations to demonstrate adequate flow and pressure. To conduct these calculations, water data is essential. Moreover, if you are fed directly from the municipal supply, you need water data from within the past year.

The building code specifies the respective scope area, contingent on the level of alteration. However, this still necessitates the contractor to provide calculations proving that the renovation doesn't affect system performance.

The scope area shields the contractor from having to address code violations outside of the specific project's parameters.

Reply
Jesse
8/10/2023 08:11:09 am

This is a really good question, and should be a good discussion.

In my state (Texas), the person signing the plans is the license holder. For system modifications, they are attesting that not only the modifications meet code, but the remainder of system still does as well.

In some of our AHJs, they require hydraulically calculating the system. Even when it doesn't, sometimes I require it because ultimately I'm signing it.

I think every answer may be different depending upon the state.

Reply
Daniel LeFave
8/10/2023 08:17:58 am

As a contractor, we always specify in our scope of work that we start at a flange above floor and furthermore specify what we intend to provide for our services. This does not limit us to new hydraulic calculations and often we perform a new hydrant flow test or water data has been provided to us along with the new/updated design criteria by the engineer of record. For example, we recently had a warehouse job and the GC limited us to the office scope only as there was an existing system in the warehouse, but the occupancy was changing. The AHJ requested that calculations be performed in the warehouse to the new system demand requirement and after a bunch of back and forth it was decided this was a requirement for TCO and we were contracted to calc the system. It seems that most GC's and owners only care about drywall going up until TCO time comes around and then they remember about the life safety systems.

Reply
Dan Wilder
8/10/2023 08:54:20 am

First, what provisions are adopted within the IFC, specifically Section 105.6 for required permits? Then, referencing 106.2.2 for the requirements of Shop Drawings per Chapter 9.

901.2 for Construction Document requirements and your rights as an AHJ as to what is expected.

NFPA 13-22' Chapter 30 for Existing System Modifications has a decent breakdown for allowances & requirements.

Do you have anything within your adopted fire code or within the fire prevention department as to specific policies/procedures/checklists that would require this? At least have some justification so that I as a contractor can go back to the owner and have backup for the additional costs being incurred.


As to the described work.

Sprinkler change out - While not the place I would setup a stoppage for, due to NFPA 25's requirements for replacement and assuming that the sprinkler change out is like for like (K-Factor specifically). While this part may trigger a plan review for scope of area or at a minimum a scheduled inspection for compliance review, requiring hydraulics based on this alone seems excessive when there are no other changes.

Pipe change out - Again, if this is like for like due to something like leaks (pipe schedule and size of pipe), in itself not a hydraulic triggering event.

Now, put both together and review if the property has undergone any occupancy changes or renovations, that would be the trigger for plan review at a minimum, but this is still grey as to a hydraulics review for just those two items.

Other items like occupancy changes or unpermitted remodels (like the new office mezz area in the corner of the warehouse), a known water supply degradation in the area, NFPA 25 inspection reports indicating main drain test degradation, anything high piled storage related, any addition of valves (backflow), any addition of flex hoses... would justify a hydraulic review.


One of my AHJ's adopted changes that trigger plan review for reference:

903.3.10 Remodel. Fire sprinkler design drawings shall be required for tenant improvement or remodeling projects when 10 or more sprinkler heads are relocated and/or added.
Exception. Group F, H, I, and S or as required by the fire official

Another has a "Quick Permit" for various smaller items like modifications under 20 sprinklers but there is a provision that the inspector can ask for a full plan review upon inspection.

Reply
Glenn Berger
8/10/2023 09:09:06 am

To your original question - Does your jurisdiction is construction permits and certificate of occupancies?

If yes then stick to your guns and be prepared to act like (and be treated like) a specific body part.

The sprinkler contractor may have a limited scope (as stated above), but someone else owns the greater scope. Someone needs to held accountable for code compliance.

Reply
SCHULMAN
8/10/2023 09:22:24 am

Lots of good info in the responses already.
Yes, you can require a new flow test and calcs. You are the AHJ ...
Unless this is design-build scenario or the contractor is the lead, It's generally not the contractor's problem if the project scope didn't include it. The owner and the consulting firm housing the FP Designer should have asked you pre-permit if you were going to require it and the money would be in place. That's on them. Designers - ALWAYS contact your AHJ during design !...

Here's what I didn't hear above that I think should always be considered - in some areas development is rampant, and flows are impacted by additional mouths to feed on the system... Unless the area has zero new buildings, i would definitely require new flows/calcs. My 2 cents.

Reply
Eric R
8/10/2023 11:43:26 am

To add to the discussion, what happens (or should happen) when the contractor does get a new flow test, performs hydraulic calculations for the scope of their work (which can be easily modified if need be within the scope of work), applies for a permit showing their work has the required water supply, but the flow test shows that the water supply has degraded below what was required for the original system design per the hydraulic placard?

This kind of veers into NFPA-25 territory and the lack of clarity on if/when sprinkler systems on municipal water should have their water supply validated. Having the requirement to flow-test the water supply of an existing sprinkler system "hidden" away in the private service main chapter of NFPA-25 causes many contractors and AHJs to not realize that it is required at all. If the private service main feeding the sprinkler system is getting flow tested every 5 years then should this test data be acceptable to use for the hydraulic calc?

Then there is also the question that if a system does have a hydraulic placard, can the contractor just prove that their scope of work does not create a greater hydraulic demand than the currently posted one and avoid the need to get a flow test at all? In this case how does the AHJ confirm that the hydraulic placard has accurately recorded the design data of the original system? Without the original set of hydraulic worksheets I would personally be very leery of accepting a system modification based on just the placard since they are so frequently filled out incorrectly.

Reply
Pete H
8/10/2023 02:03:51 pm

IMO (so take with grain of salt):

The contracted work will still work and has been proven by calculation. That is still approved. However an AHJ (typically a fire marshal) that is aware the water supply has degraded to a point the previously approved and installed system will no longer work needs to either inform the property owner that they're responsible for another renovation to get the system up to/prove the system still works according to current code and they must get started on scheduling that work. And then if the work does not seem like it's moving forward after a year (the speed of bureaucracy), penalize them accordingly.

The flow test from a 5 year inspection, if on the water source that supplies the system, should be able to be duplicated and used for a hydraulic calculation. But it has to be duplicated, you can't just say "refer to inspection report." You still have to give a separate copy of the flow test results in your working plan submission that has nothing to do with the 5 year inspection. Once again, for bureaucracy. But you should be able to use that source information on your calc if it is at the correct point of the incoming service to be applied to this calculation.

Yes, they can prove their demand is less than the hydraulic placard on the existing system. This even can be done if they're working on a system that just happens to be of a significantly lesser hazard and demand than the existing.

Like you have a K28 gridded ESFR system protecting the storage facility at the roof of a near 40'-0" building.

If you tap off that main to feed two 5.6k heads in < 100 sq. ft. bathrooms and offices with less than 10'-0" ceiling height and these rooms are even closer to the source than the existing remote area.... you don't need to calculate that. This system can obviously handle that additional demand at a separate elevation.

Reply



Leave a Reply.

    SUBMIT A QUESTION
    Picture
    Why Sponsor?

    ALL-ACCESS

    Picture
    GET ALL OUR TOOLS

    SUBSCRIBE

    Subscribe and learn something new each day:
    I'm Interested In:

    COMMUNITY

    Top Oct '25 Contributors
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    SEE LEADERBOARD

    YOUR POST

    SUBMIT A QUESTION

    PE EXAM

    Get 100 Days of Free Sample Questions right to you!
    SIGN ME UP!

    FILTERS

    All
    A1171
    ABA
    ADA
    ASCE 7
    ASME A17.1
    ASTM E1354
    Blog Thread
    Daily Discussion
    Design-documents
    EN 12259-1
    EN 12845
    Explosion Protection
    Explosion-protection-prevention
    Fire Detection And Alarm Systems
    Fire Dynamics
    Flammable And Combustible Liquids
    Flammable-combustible-liquids
    FM Global
    Human-behavior
    IBC
    ICC 500
    IEBC
    IFC
    IMC
    IPC
    IRC
    ISO
    Means Of Egress
    NBC
    NFPA 1
    NFPA 10
    NFPA 101
    NFPA 11
    NFPA 110
    NFPA 1142
    NFPA 1221
    NFPA 13
    NFPA 13D
    NFPA 13R
    NFPA 14
    NFPA 15
    NFPA 16
    NFPA 17A
    NFPA 20
    NFPA 2001
    NFPA 214
    NFPA 22
    NFPA 220
    NFPA 24
    NFPA 241
    NFPA 25
    NFPA 291
    NFPA 30
    NFPA 307
    NFPA 30B
    NFPA 31
    NFPA 33
    NFPA 37
    NFPA 400
    Nfpa-409
    Nfpa-415
    Nfpa-45
    Nfpa-495
    NFPA 497
    NFPA 5000
    NFPA 502
    NFPA 54
    NFPA 55
    NFPA 654
    NFPA 68
    NFPA 70
    NFPA 701
    NFPA 72
    NFPA 75
    NFPA 770
    NFPA 82
    NFPA 850
    NFPA 855
    NFPA 90A
    NFPA 92
    NFPA 96
    NICET
    OBC
    OSHA
    Passive Building Systems
    PE Prep Guide
    PE Prep Series
    PE Sample Problems
    Poll
    Smoke Management
    Special Hazard Systems
    UFC 3-600-01
    UFC 4-021-01
    UFC 4-211-01
    UPC
    Updates
    Water Based Fire Suppression
    Weekly Exams


    ARCHIVES

    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    November 2016
    October 2016
    July 2016
    June 2016


    PE PREP SERIES

    SEE LEADERBOARD

    RSS Feed

Picture
​Home
Our Cause
The Blog
The Forum
PE Exam Prep
The Toolkit

MeyerFire University
​Pricing
Login
​Support
Contact Us
Picture

MeyerFire.com is a startup community built to help fire protection professionals shine.
Our goal is to improve fire protection practices worldwide. We promote the industry by creating helpful tools and resources, and by bringing together industry professionals to share their expertise.

​MeyerFire, LLC is a NICET Recognized Training Provider and International Code Council Preferred Education Provider.

All text, images, and media ​Copyright © 2016-2025 MeyerFire, LLC

We respect your privacy and personal data. See our Privacy Policy and Terms of Service. 
The views, opinions, and information found on this site represent solely the author and do not represent the opinions of any other party, nor does the presented material assume responsibility for its use. Fire protection and life safety systems constitute a critical component for public health and safety and you should consult with a licensed professional for proper design and code adherence.

Discussions are solely for the purpose of peer review and the exchange of ideas. All comments are reviewed. Comments which do not contribute, are not relevant, are spam, or are disrespectful in nature may be removed. Information presented and opinions expressed should not be relied upon as a replacement for consulting services. Some (not all) outbound links on this website, such as Amazon links, are affiliate-based where we receive a small commission for orders placed elsewhere.

  • Blog
  • Forum
  • TOOLKIT
    • ALL TOOLS
    • BUY THE TOOLKIT
  • UNIVERSITY
    • ALL COURSES
    • JOIN THE UNIVERSITY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE PREP SERIES
    • PE 100-Day Marathon
  • LOGIN
    • TOOLKIT-ONLY LOGIN
    • UNIVERSITY LOGIN
  • STORE
  • OUR CAUSE
    • ABOUT MEYERFIRE
    • JOB OPENINGS
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT