Any BIM sprinkler coordinators here? What is your experience in estimating design effort for BIM Coordination?
Do you charge by the head or by hour? The last hospital I coordinated took 4 hours per sprinkler. Posted anonymously for discussion. Discuss This | Submit Your Question | Subscribe
9 Comments
Dan Wilder
4/28/2020 09:11:15 am
Our approach is 75-100% increase from the base design hours amount at a minimum depending on the building (hospitals being the worst down to open warehouse ESFR). It's not so much that our design will actually take that long, but sitting in meetings and other trades being reactive to a design causes a lot of go backs.
Reply
federico pacheco
4/29/2020 11:54:04 am
This is certainly true specially in countries where each trade works independently, and the "BIM" QA/QC is done at field, where cost overruns are the rule.
Reply
James
4/28/2020 10:24:00 am
We start with a minimum of adding 50% more to design. We add hours from there, depending on the complexity of the project.
Reply
Greg Stoner
4/28/2020 10:34:53 am
I am looking forward to hearing ideas on this great topic. As an estimator, BIM is a challenge for me. I estimate design hours separately and add BIM meetings in afterwards based on the project schedule.
Reply
NK
4/28/2020 10:41:35 am
Projects with designated BIM coordinators typically have BIM coordination schedules. While the schedule might not be contractually binding, it can be helpful to see how many meetings per week the BIM Coordinator is planning and how long each meeting will be. You might not be able to get this information if you are bidding in the early stages of a project, but it's worth asking for. It would be very difficult for the BIM coordinator to estimate their own cost without being able to estimate a quantity of meetings and the duration of meetings. The level of BIM and expected project deliverables are also things to consider.
Reply
Cliff
4/29/2020 07:08:31 am
Word to the wise, BIM coordination schedules are rarely realistic
Reply
Mike
4/28/2020 11:40:46 am
I appreciate the feedback. I had estimates of at least the initial design hours and up to 3 hours if it's OSHPD.
Reply
CJ Bonczyk
4/28/2020 12:18:50 pm
A few tips from my long tenure in the world of BIM/VDC.
Reply
Adam Bjorkman
4/29/2020 07:36:02 am
For estimating BIM projects I normally double the design time. It normally depends on the size of the job though. The trouble that we are running into right now is projects that were never figured for doing BIM that are turning into that kind of job with trades running the clashes and using it for coordination efforts, it will add to our design hours, but we have seen good return on field labor hours. I'd say the majority of projects now are about half modeled. We have been working closely with HVAC companies who are on board with coordinating everything this way, but working with electrical trades is more of a challenge. I feel like the sprinkler industry has been way ahead of this for a long time, pre-fabricating most of our piping we want to get everything in the right spot before fabrication starts, its nice to see others doing the same finally.
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop November '24 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
December 2024
PE PREP SERIES |