Why Are We Still Separating Fire Alarm Equipment Submittals From the Shop Drawings?
I’m looking for input from the engineering community on something I continue to struggle with in the typical A/E submittal process. On many projects, the fire alarm equipment/product data is submitted early, and the actual fire alarm shop drawings, calculations, riser, sequence of operations, interfaces, circuiting, and other system-design information follow later. This appears to be a long-established A/E practice, but I increasingly question what meaningful engineering review is supposed to occur at that first equipment-only step. With product data alone, I can determine that the proposed manufacturer is acceptable, that the equipment family generally complies with the specification, and that I do not see an obvious reason the contractor should be prevented from purchasing the equipment. What I cannot legitimately determine is whether the equipment package is complete, properly sized, properly configured, or sufficient for the actual fire alarm system. Until I see the shop drawings and calculations, I do not know whether the contractor has provided the correct quantities and capacities of panels, power supplies, amplifiers, modules, network equipment, batteries, interfaces, survivability components, and everything else required to make the system work as intended. Because of this, I have actually revised my own fire alarm specifications to require the product data, shop drawings, calculations, sequence of operations, and associated system-design information to be submitted together as one coordinated system submittal. Yet I continue to see the industry separate them anyway. And that is part of what I am trying to understand. Is there a real technical or contractual reason for doing this, or are we simply continuing a process because “that’s how we’ve always done it”? I struggle with that mentality, particularly when the established administrative process does not appear to fit the way an engineered system actually needs to be reviewed. I recently had a situation that highlighted the problem. The proposed equipment itself was acceptable, but the overall submittal had to be formally rejected because the required shop drawings had not been provided. I specifically indicated that I had no objection to the proposed equipment, but because the official disposition was Rejected, the contractor would not release the equipment for purchase. That seems like a contradiction created by the process itself. I do not want to give an unconditional approval to an equipment package when I have not yet seen enough of the system design to support that approval. At the same time, I do not want the contractor prevented from purchasing equipment that I have reviewed and have no technical objection to them procuring. What I would really like to be able to communicate is something along these lines: No objection to procurement of the proposed manufacturer and equipment. This review does not constitute acceptance of equipment quantities, capacities, configuration, system architecture, interfaces, calculations, or overall system completeness. Those items remain subject to review of the complete coordinated fire alarm shop-drawing submittal. There is also a separate review-time issue that compounds the problem. On projects with a nominal two-week A/E submittal review period, the fire protection engineer may not actually receive the package until it has already passed through the subcontractor, electrical contractor, GC, and Architect. In practice, I may receive it with only two or three days remaining. For a complete fire alarm submittal containing drawings, calculations, product data, sequences, interfaces, and specification requirements, I also question how the industry expects a legitimate engineering review to occur under that compressed timeframe. So the three questions I keep coming back to are: 1. Why are we still separating fire alarm equipment from the shop drawings, calculations, sequence, interfaces, and other system information needed to actually evaluate it? 2. How do we allow the contractor to purchase technically acceptable equipment without giving an engineering approval that the information submitted does not yet support? 3. How do we change the “this is how it’s always been done” process so the complete fire alarm system submittal can be submitted together—and the engineer is actually given enough time to perform a legitimate review? I would especially like to hear from people who know why this sequencing developed in the first place, but also from those who have successfully changed their specifications, contracts, routing, or submittal schedules to make a complete coordinated review possible. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
8 Comments
Pete H
10/6/2026 06:17:23 am
1) Timing and Space. We want to look at product data for budgeting as much as we do for evaluation. We want to do that before we pay someone to design the project. So submittals are filed before the shop drawing, this way if the design team takes issue with an item on the submittal: it is resolved before the shop drawing design. Also, it's minimum an extra page of drawings that the field techs don't need because they get copies of the tech specs and catalog cuts with the material shipments.
Reply
Dan Wilder
10/6/2026 08:09:32 am
1. Submittal of equipment of the equipment generally aligns with a design that is viable for submittal. If a Contractor only submits on strobes, but the design requires audio notification, that is an identifiable miss in the submittals. Once I get that approval, I still don't have an approval on the design so if purchasing occurs, the responsibility is still on me (see 2).
Reply
chad
10/6/2026 08:15:37 am
1- Its not taken seriously enough by owners, architects and AHJ's. We collectively need to hold a standard
Reply
Brian Gerdwagen
10/6/2026 08:59:57 am
1. A number of right answers have been given. The separation allows us to verify that the products meet the spec before shop drawings are started. Many times a client will request a specific manufacturer only for the contractor to submit a different one. Do we fire the sub because they can't install the requested products?
Reply
Jeff Ayers
10/6/2026 09:31:47 am
On 99% of the projects completed over the last 40 years, the FA and Sprinkler are Delegated Design.
Reply
chad
10/6/2026 09:43:20 am
This is the problem.
Reply
Jeff Ayers
10/6/2026 09:56:47 am
You are correct. The AHJ review and the EOR review is usually an overview only. They both end up stamping language that basically states "reviewed for general conformance" & "device types and locations must meet IFC"... or NFPA or whatever code the building is subject to.
chad
10/6/2026 10:12:35 am
Another good point.... no one checks the details and then we are all waiting on rework. If we put the time in it initially, the final AHJ inspection should be easy and boring. I am critical on plan details like that, along with a proper I/O Matrix so we are not standing there waiting on the programmer to redo mapping.
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop Oct '26 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
November 2026
PE PREP SERIES |
RSS Feed