MeyerFire
  • Blog
  • Forum
  • THE TOOLKIT
    • SUBMIT AN IDEA
    • BACKFLOW DATABASE*
    • CLEAN AGENT ESTIMATOR*
    • CLOUD CEILING CALCULATOR
    • DOMESTIC DEMAND*
    • FIRE FLOW CALCULATOR*
    • FIRE PUMP ANALYZER*
    • FIRE PUMP DATABASE*
    • FRICTION LOSS CALCULATOR
    • HANGER SPACER*
    • IBC TRANSLATOR*
    • K-FACTOR SELECTOR*
    • NFPA 13 EDITION TRANSLATOR ('19 ONLY)
    • NFPA 13 EDITION TRANSLATOR ('99-'22)*
    • LIQUIDS ANALYZER*
    • OBSTRUCTION CALCULATOR
    • OBSTRUCTIONS AGAINST WALL*
    • PLUMBING FIXTURE COUNTS
    • QUICK RESPONSE AREA REDUCTION
    • REMOTE AREA ANALYZER*
    • SPRINKLER DATABASE*
    • SPRINKLER FLOW*
    • SYSTEM ESTIMATOR*
    • TEST & DRAIN CALCULATOR
    • THRUST BLOCK CALCULATOR
    • TRAPEZE CALCULATOR
    • UNIT CONVERTER
    • VOLUME & COMPRESSOR CALCULATOR
    • WATER STORAGE*
    • WATER SUPPLY (US)
    • WATER SUPPLY (METRIC)
  • UNIVERSITY
    • ABOUT
    • CATALOG
    • CONTENT LIBRARY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE Prep Series
    • PE 100-Day Marathon
  • LOGIN
  • PRICING
    • SOFTWARE & TRAINING
    • STORE
  • THE CAUSE
    • ABOUT US
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT
Picture

Who is Ultimately Responsible for a Design-Build Fire Protection Design?

4/12/2021

12 Comments

 
My question is more based on principle rather than design.

I have been in the industry for over years and keep coming to the same question lately; who is responsible for the end product on design and install?

I've had several projects in the last year where a "mechanical engineer (plumbing/HVAC)" are doing the layout for the schematic and bid drawings and don't have the complete knowledge of fire protection. I've had to deal with issues ranging from head spacing to pump specifications... and none of them have been close to code.

Specifically, I have a 3-story building with the 3rd floor at 30'-0" above apparatus / grade so there should be no need for standpipes. The plan/specs require an automatic-wet standpipe with a 125 psi @ 500 pump. I sent an RFI on why the need for the automatic-wet standpipes, where we can do away with standpipes or go to manual/wet and I was rejected. Ultimately, we were told to follow the prints....but we are "delegated" design. Eliminating the pump and standpipes, we could have saved the county $110,000+ (electric included).

I now have a church with 36-ft throw sidewalls and the engineer would like to stay with sidewalls and not have any pipe crossing the room; it's not possible with the supply.

In the end, who is responsible for the design and performance of the system?

If the contractor follows the plan/spec, is he liable because he is the "delegated" designer? But if the delegated design needs to change and is rejected, who is liable?

How do you bid plan and spec project if there are multiple issues with the bid plans? Do you redesign and bid it correct? No, you won't get the job. Or, do you bid per prints and then not be allowed change orders because you are the delegated designer?

​​​​​​​​​​​​​​​​​​Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
12 Comments
FIREPE25
4/12/2021 08:08:16 am

In my state (MA) the engineer of record would be the individual who supplied the construction control form for the project. He will also be the one who provides the final affidavit. If you are the one acting as the engineer of record then it should be you making the calls. In situations where we are not the engineer of record we submit RFIs informing them that what they did is incorrect. If they disagree we get second opinions and letters from industry experts like NFSA/AFSA, etc. If they still disagree depending on how large of an issue it is we get fire marshal involved. In some instances we will advise them that our company disagrees with there position but will proceed under there direction as the engineer of record, but will not take on any liability for the specific situation.

Reply
JAMES
4/12/2021 08:15:28 am

I feel like this is a very responsible position to take as a contractor.

To me if the consultant requires the contractor to provide their own engineer then they no longer have a basis to demand something outside of code. Personally, I feel like it is one or the other; either the consultant must own the project and decisions (including liability) as the EOR, or defer it and cede control for some of these decisions where the actual engineer of record (the contractor's) can provide what they feel and are charged with as being code compliant.

Reply
Glenn Berger
4/12/2021 08:12:24 am

There is no one person who is ultimately responsible. Responsibility is on everyone involved. Including the errors made by the bogus design and specifier to the installer and the AHJ. The owner is also responsible to ensure that the conditions of the approved design are maintained.

Reply
Mike
4/12/2021 08:15:51 am

In my experience, it's always been prudent to submit RFI's about the obvious mistakes prior to bid. Then you and the other contractors are on equal grounds for scope and cost.

If submitted after the bid, there will be chances of bigger and more costly arguments.

Reply
Jesse
4/12/2021 08:20:49 am

That's a tricky question, and the answer would be dependent upon which state you are in.

In Texas, it's a little more streamlined. The design engineer signing sprinkler / standpipe / underground fire line plans must be licensed by the state specifically for this discipline. So, a mechanical engineer or architect can't design water-based protection. same thing with alarm.

As an insurance HPR engineer previously, I've seen some really crazy things in AS design, and it typically stems from people designing these that shouldn't be.

I'd consult your state fire marshal's office, but yeah, it's convoluted

Reply
Kelley Stalder link
4/14/2021 09:30:28 am

I think you'll find many fire sprinkler systems in Texas designed by mechanical or even civil engineers. Texas also licenses fire sprinkler contractors to design fire sprinkler systems and fire alarm contractors to design fire alarm systems.

Reply
James Phifer
4/12/2021 08:22:39 am

Where do you find a 36 foot throw sidewall? I've never seen one throw more than 26 foot long.

Reply
JAMES
4/12/2021 08:25:37 am

A 2-1/2" open hose... or a water cannon!

Reply
Matt
4/12/2021 08:31:50 am

It depends on who you are bidding to and how well you know them.

If the owner/gc are going to be unreasonable in their demands and you can't get high enough price - then you probably don't want the job (unless you need some install practice).

I have had the situation you talk about come up where the gc tries to lay every possible issue in our lap because it is "design build". I like to say: "I will design-build a car if you want one, but you can't blame me when it is not a boat."

Tell them what you are going to give them and then deliver that. Just be sure you clarify EXACTLY what you are providing for the price you offer. And try not to get into deals with unscrupulous folks who want a bunch of unpaid changes.

Reply
Dan Wilder
4/12/2021 09:47:35 am

This is a fun one due to working relationships, reputation, and responsibility.

Firstly, we bid projects per the plans and specifications provided because those documents are contractual and enforceable. However, we do RFI (or other forms of written communication) any large issues we see that would go against an installation requirement. In your example, while not required, providing items above the minimum is not something my company would "go to war" with. The same process of providing an RFI to eliminate based on the lack of requirements would be followed and if the owner (or GC as the middle man) still wanted to spend the money, so be it.....it's getting installed per NFPA. If they want copper piping (and yes, we have 3 current projects with the request), they get copper instead of steel.

Inversely, if we request things like a larger pump (GPM/PSI or both) to handle what will be a future buildout (say a low riser that has future high rise phase or a current office design in what will be a warehouse) and try to give the owner the chance to upsize the pump now vs having to buy another pump for the expansion or retrofit a new pump and that gets denied, then fine, we tried and have documentation (and yes, this also occurred on a project where the owner used the future warehouse as an assembly area and is now needing high piled storage with in-racks in a light hazard space - we specifically kept that RFI response handy and presented it when the owner pulled us into a meeting....while not happy, that focus shifted away from us as trying to be "change order happy", we currently hold all their ITM/Hood/FX & FA contracts because of the relationship).

In the example of the sidewalls throwing further than listed, that is one we will fight unless they want to provide a FPE report defining the allowance for an unlisted installation (it's not unheard of, just rarely used). You as the contractor are not providing design/engineering at this point, just installing what is being specified and as long as its installed per that FPE report, you should be covered.

We see mechanical drawings providing FP design a lot, same process with the RFI's (be it installation requirements, listing issues, coordination and working away from whatever was specified), but along you can also use the notes on the drawings that typically state something like "Drawings are diagrammatic in nature or show design intent only, actual installation shall be the responsibility of the installing contractor..." this is a good out that we use to just show the NFPA section that corresponds with the actual shop drawing creation.

In an absolute worst case, where the engineer is practicing outside there area of expertise, we will ask some of our contacts in their engineering world to "off the record" give them a chance to revise items accordingly. We have also requested and brought in our own FPE to help. We have not taken a PE in front of the board for a formal complaint, but the discussion has been had as a possible next step.

Ultimately, documentation is your best friend, use your sales bids to include/exclude as much as possible - making sure it makes it into the contract language, but if they are asking for more then clarify that's want they really want (and make sure it's priced accordingly), if it falls short of the minimums then RFI and provide the backup. The installing contractor is still required to provide a working, code compliant installation. The design still needs to comply as well but SFPE has been very clear on the roles & responsibilities delegated.

https://www.nspe.org/resources/issues-and-advocacy/professional-policies-and-position-statements/sfpenspenicetascetncees

Reply
David J Branson
4/12/2021 09:52:14 am

There will be only one Engineer-of-Record (EoR) per Project discipline or subdiscipline. If the General Contractor is tasked with providing design along with construction, then the GC's FPE would provide the Fire Protection design. The scoping documents provided as bid documents must be considered as they represent the Owner's Project Requirements (OPR) and Basis of Design (BoD). If the bid documents convey a design that cannot meet code, the conflict should be surfaced immediately in an RFI. If the conflict still remains, the AHJ should be brought into the situation for their interpretation of the code issue in question. The Insurance underwriter for each party should also be consulted to protect their insured.

Reply
Alex Abossein, FPE, MPE, EPE link
4/14/2021 04:41:55 pm

There is only one engineer of records and he/she is the one who has fully designed, engineered and calculated and sealed and has signed the construction documents via design drawings. His/her dwgs. can not be deviated without his/her approval and if they are wrong then he/she is the responsible liable party to correct and to reissue them accordingly.

Any other documents issued for bid/construction that is intended to be designed and completed by the bidders/others to define the scope for bidding are considered bidder designed documents and the engineer/architect/owner/etc. who prepared them is not considered to be the engineer or DOR. It is mainly to provide some criteria and preferences that the owner may want as far as aesthetics, heads in center of tiles or lined up with lights, and generic location of piping, etc. that are more provided as a wish list items to be evaluated and incorporated into the design where possible when/if not conflicting with any codes and standards that maybe evaluated by the designer.

If the owner has a consultant acting on his behalf to provide some generic bidding documents that are not considered fully designed/sealed/signed documents then that consultant can only enforce the contractors to do that part of the work that are considered optional and non-technical wish list items such as extra heads to create more linear patterns that it would have normally be needed, or wall vs. ceiling heads, etc.

The ultimate design responsibility and liability will be on the person whose seal and signature will appear on dwgs along with his civil contractual liability to the owner remaining to be providing the extra heads, provisions, etc. that the owner, wanted as a part of the contract wish list when not conflicting with codes, standards and sound engineering practices.

Reply



Leave a Reply.

    Picture
    Why Sponsor?

    ALL-ACCESS

    Picture
    GET ALL OUR TOOLS

    SUBSCRIBE

    Subscribe and learn something new each day:
    I'm Interested In:

    COMMUNITY

    Top ​Feb 2023 Contributors
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    Picture
    SEE LEADERBOARD

    YOUR POST

    SUBMIT A QUESTION

    PE EXAM

    Get 100 Days of Free Sample Questions right to you!
    SIGN ME UP!

    FILTERS

    All
    A117.1
    ABA
    ADA
    ASCE 7
    ASME A17.1
    ASTM E1354
    Daily Discussion
    Design Documents
    EN 12845
    Explosion Protection & Prevention
    Fire Detection And Alarm Systems
    Fire Dynamics
    Flammable & Combustible LIquids
    FM Global
    Human Behavior
    IBC
    ICC-500
    IFC
    IMC
    IPC
    IRC
    ISO
    Means Of Egress
    NBC
    NFPA 1
    NFPA 10
    NFPA 101
    NFPA 11
    NFPA 110
    NFPA 1142
    NFPA 1221
    NFPA 13
    NFPA 13D
    NFPA 13R
    NFPA 14
    NFPA 15
    NFPA 16
    NFPA 17A
    NFPA 20
    NFPA 2001
    NFPA 214
    NFPA 22
    NFPA 220
    NFPA 24
    NFPA 241
    NFPA 25
    NFPA 291
    NFPA 30
    NFPA 30B
    NFPA 33
    NFPA 400
    NFPA 409
    NFPA 415
    NFPA 495
    NFPA 497
    NFPA 5000
    NFPA 502
    NFPA 54
    NFPA 55
    NFPA 654
    NFPA 68
    NFPA 70
    NFPA 701
    NFPA 72
    NFPA 75
    NFPA 770
    NFPA 82
    NFPA 855
    NFPA 90A
    NFPA 92
    NFPA 96
    NICET
    OBC
    Passive Building Systems
    PE Prep Guide
    PE Prep Series
    PE Sample Problems
    Poll
    Smoke Management
    Special Hazard Systems
    UFC 3 600 01
    UFC 3-600-01
    UFC 4-021-01
    Updates
    Water Based Fire Suppression
    Weekly Exams


    ARCHIVES

    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    November 2016
    October 2016
    July 2016
    June 2016


    PE PREP SERIES

    Fire Protection PE Exam Prep
    SEE LEADERBOARD

    RSS Feed

Picture
​Home
Our Cause
The Blog
The Forum
PE Exam Prep
The Toolkit

MeyerFire University
​Pricing
Login
​Support
Contact Us
Picture

MeyerFire.com is a startup community built to help fire protection professionals shine.
Our goal is to improve fire protection practices worldwide. We promote the industry by creating helpful tools and resources, and by bringing together industry professionals to share their expertise.

​MeyerFire, LLC is an International Code Council Preferred Education Provider.

All text, images, and media ​Copyright © 2023 MeyerFire, LLC

We respect your privacy and personal data. See our Privacy Policy and Terms of Service. 
The views, opinions, and information found on this site represent solely the author and do not represent the opinions of any other party, nor does the presented material assume responsibility for its use. Fire protection and life safety systems constitute a critical component for public health and safety and you should consult with a licensed professional for proper design and code adherence.

Discussions are solely for the purpose of peer review and the exchange of ideas. All comments are reviewed. Comments which do not contribute, are not relevant, are spam, or are disrespectful in nature may be removed. Information presented and opinions expressed should not be relied upon as a replacement for consulting services. Some (not all) outbound links on this website, such as Amazon links, are affiliate-based where we receive a small commission for orders placed elsewhere.

  • Blog
  • Forum
  • THE TOOLKIT
    • SUBMIT AN IDEA
    • BACKFLOW DATABASE*
    • CLEAN AGENT ESTIMATOR*
    • CLOUD CEILING CALCULATOR
    • DOMESTIC DEMAND*
    • FIRE FLOW CALCULATOR*
    • FIRE PUMP ANALYZER*
    • FIRE PUMP DATABASE*
    • FRICTION LOSS CALCULATOR
    • HANGER SPACER*
    • IBC TRANSLATOR*
    • K-FACTOR SELECTOR*
    • NFPA 13 EDITION TRANSLATOR ('19 ONLY)
    • NFPA 13 EDITION TRANSLATOR ('99-'22)*
    • LIQUIDS ANALYZER*
    • OBSTRUCTION CALCULATOR
    • OBSTRUCTIONS AGAINST WALL*
    • PLUMBING FIXTURE COUNTS
    • QUICK RESPONSE AREA REDUCTION
    • REMOTE AREA ANALYZER*
    • SPRINKLER DATABASE*
    • SPRINKLER FLOW*
    • SYSTEM ESTIMATOR*
    • TEST & DRAIN CALCULATOR
    • THRUST BLOCK CALCULATOR
    • TRAPEZE CALCULATOR
    • UNIT CONVERTER
    • VOLUME & COMPRESSOR CALCULATOR
    • WATER STORAGE*
    • WATER SUPPLY (US)
    • WATER SUPPLY (METRIC)
  • UNIVERSITY
    • ABOUT
    • CATALOG
    • CONTENT LIBRARY
  • PE Exam
    • PE Forum & Errata
    • PE Store
    • PE Tools
    • PE Prep Series
    • PE 100-Day Marathon
  • LOGIN
  • PRICING
    • SOFTWARE & TRAINING
    • STORE
  • THE CAUSE
    • ABOUT US
    • BECOME AN INSTRUCTOR
    • HELP/SUPPORT