|
We have encountered a situation not fully addressed before in our jurisdiction.
Scenario: Existing fully sprinklered hospital having renovation work done in multiple areas and floors. Some phases of work take months, others take 6+ months to complete. After ICRA walls (Infection Control Risk Assessment / temporary walls to isolate construction areas) are installed, the GC will remove the existing ceilings and commence with architectural demolition. At that time, we (sprinkler contractor) came in and removed the existing pendent sprinklers and replaced them with upright heads on short 3" sprigs (without regard to obstructions or distance down from structure). This is due to existing MEP trades yet to perform their scope of work, ie: HVAC, Plumbing demo, then new install. NFPA 241 indicates that the temporary upright sprinklers need to be installed with regards to the obstructions per NFPA 13. At this phase of construction, that would necessitate installing the upright sprinklers for ductwork that is scheduled to be demolished in a few weeks along with other MEP trades. By following the sprinkler obstruction rules of NFPA 13, the net effect is that we would constantly be relocating the temporary protection at the same time each trade completes a portion of their work. This issue has just arisen recently based upon an AHCA site visit (Agency for Health Care Administration). Prior installations of the uprights without obstruction spacing rules has not been called out. How has this issue of temporary sprinkler protection for buildings under renovation been delt with by others? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
11 Comments
Chad
1/30/2026 08:11:29 am
Depends regarding the severity obstructions IMO, need to look at it holistically. But if its a serious concern make them comply 100%.
Reply
NK
1/30/2026 08:27:20 am
NFPA 241, 2022 Standard for Safeguarding Construction, Alteration, and Demolition Operations §4.3.2.3 states “Systems temporarily placed in service during construction shall not be required to comply with NFPA standards.” The annex provides additional guidance in A.4.3.2.3 by saying “Whereas the permanent fire protection systems are required to meet NFPA standards, systems placed in service temporarily during construction are subject to different and varying conditions than those used in full-scale fire tests to verify the installation criteria of sprinkler systems. Conditions that differentiate the permanent protection from the temporary protection include, but are not limited to, the lack of finished ceilings, lack of finished walls, protective sprinkler caps being in place, obstructions present during construction, exposed wood construction, fuel loading of construction materials, and lack of heat.”
Reply
Joe M
1/30/2026 08:41:36 am
Based on NFPA 241, 2022 edition, what does the Fire Protection program require?
Reply
Brett
1/30/2026 08:58:25 am
They mentioned AHCA so this must be in Florida (OP correct me if I'm wrong). Florida uses the 2019 edition of NFPA 241 right now. That said, there's no harm in showing the AHCA officials this section in the 2022 edition.
Reply
CK
1/30/2026 10:29:57 am
Correct south Florida
Anthony
1/30/2026 08:43:15 am
I think this is an instant where something is better than nothing. Get a conversation with the AHJ started. Sprinklers everywhere with some obstruction is vastly better than no sprinkler. I'd also argue temporary fire detection (alarms) would be a positive part of the plan. Probably heat detectors as many construction activates will produce dust.
Reply
Todd E Wyatt
1/30/2026 08:49:42 am
Some AHJs will permit a Construction Barrier with a 2-Hr fire-resistance rating (FRR) to separate Construction Areas that do not meet the requirements (NFPA 101 LSC-2012 + IBC) for the adjacent occupied Existing Health Care (LSC) and Group I-2 (IBC).
Reply
Jerry Clark
1/30/2026 09:30:29 am
Between NK's and Anthony's comments, you have a viable path of enforcement. Yes, we need to ensure the highest degree of safety during major renovations or reconstruction. At the same time, we must also advocate for the customer to ensure the requirements we impose on the project are not onerous or unnecessarily costly.
Reply
Dan Wilder
1/30/2026 12:13:15 pm
So, I recently went through this for a hospital complex....and it was a fight on several fronts.
Reply
OP
1/30/2026 01:44:52 pm
NFPA 241 (2022) section 4.2.2.3 state in part (as earlier comments attest) that "systems temporarily placed in service shall not be required to comply with NFPA standards". then the very next section 4.3.2.4 (1) (a) (b) (c)seem to provide guidelines for the temporary system. I am Somewhat confused between these 2 sections
Reply
1/30/2026 04:25:44 pm
The start of this section 4.3.2.1 states IF an automatic sprinkler protection is provided, it shall be placed in service temporarily in accordance with 4.3.2.2 - 4.3.2.9.
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop Feb '26 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
March 2026
PE PREP SERIES |
RSS Feed
