Does Phantom Flow apply to a 750 sqft Paint Spray booth?
Currently acting as AHJ for a spray booth sprinkler submittal. We commented that their hydraulic calculations must comply with 2022 NFPA 13 Sections 28.2.4.2.4 and 28.2.4.2.5. Are we correct in our interpretation that Section 28.2.4.2.5 requires an additional flow to be added, like a secondary hose stream allowance, so that the design discharge meets the minimum required discharge? In this specific submittal, it would require an Extra Hazard Group 2 (EH2) spray booth (approximately 750 square feet in area) to add additional flow in the calculation to meet the minimum EH2 design discharge of 1,000 gpm? (ie: 0.40 x 2500 = 1,000 gpm). The Appendix material seems to confirm this interpretation. It seems like overkill, but I cannot find an NFPA Section that would allow the minimum design area (2500 sqft) to be reduced for calculation purposes, even if the spray booth itself is only 750 sqft. Thanks in advance. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
6 Comments
Brett
12/11/2024 06:28:35 am
Phantom flow is specific to the density/area method. If the density/area method is being used then phantom flow is required. If the room design method is being used then phantom flow is not required.
Reply
Dan Wilder
12/11/2024 07:11:59 am
I would argue that if the booth falls under NFPA 33 (per 13-22 27.5), then the design provisions of the calculation area as defined within 33-19' 9.5.1 would not require it. If it referenced back to NFPA 13 for hydraulic calcs then I would apply it as you have stated.
Reply
Jaymie
12/11/2024 08:29:38 am
I think you're talking about two different things. Your design area would be .40 for 750 square feet. Your hose stream allowance for extra hazard is 500 gpm for 90 minutes so water needed when combined is 72,000 gallons.
Reply
Jesse
12/11/2024 08:58:54 am
I don't think phantom flow applies here, or at least I would pursue avennues for it not to apply. Further, I don't think the spirit of phantom flow would be appalicable.
Reply
Anthony
12/12/2024 09:04:09 am
I agree with Jesse here. the phantom flow for a fixed known hazard like a spray booth would not require enlarging the main to carry the added capacity.
Reply
Jay
12/11/2024 09:24:08 am
I had this same situation last Fall in an electric vehicle collision repair/body shop facility. I sent the questions to the NFSA, about whether or not the EH2 spray booth design was required to extend 15ft outside the booth (adjacent hazards) and if a phantom flow was required to be added due to the spray booth size (about 400 sqft) the design flow was well under the minimum 1000gpm of an EH2.
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop November '24 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
January 2025
PE PREP SERIES |