This question pertains to hydraulic calculations at the supply and sprinkler sides of a deluge system:
Our example using rough numbers; the deluge system requires 4,000 gpm based on density requirements through the building. This is the system demand. Now suppose you have a strong water supply. The water supply actually provides 8,000 gpm based on main capacity testing. This is the system supply. Now my question is, the pipe is wet up to the deluge valve. There is about 50-feet between the deluge valve and the hazard. It is understood that the system demand is 4,000 gpm, but within the pipe network, is it necessary to size the pipe for a deluge system based on 8,000 gpm on the supply side? Until the water begins discharging through the deluge nozzles, the 8,000 gpm will be surging through the pipe network to reach the nozzles, correct? Sent in anonymously for discussion. Discuss This | Submit Your Question | Subscribe
9 Comments
Glenn Berger
2/11/2021 09:19:30 am
Pipe sizes are based upon the demand requirements. Some may alter the pipe sizes to allow for greater pressure usage, if available.
Reply
Dan Wilder
2/11/2021 09:23:47 am
Supply capacity of the system is not a consideration (for this specific question, if you are working towards a containment, foam usage result, tank/break tank sizing, or a balancing requirement then a supply calc is needed). A demand calculation provides the minimum required pipe/valve sizes to make the system work. The fact the supply can provide 8000GPM (surging water has to have an outlet) and still keep the adequate pressure is just an additional safety factor to the system.
Reply
Justin Milne
2/11/2021 11:48:36 am
It makes sense, yes, I just know that there Unified Facilities Criteria codes required 10 ft/s for underground lines if you want to use ductile iron pipe. Otherwise you'd have to use PVC for the underground. Therefore, the velocity in the pipe might dictate thrust block requirements for underground depending on velocity and GPM, right?
Reply
CJ Bonczyk
2/11/2021 09:49:22 am
If its open nozzle/sprinkler style your deluge valve and piping network only needs to be sized based on the simultaneous flow of all devices downstream of the valve which as you state is the 4,000 gpm demand/the entire area protected by the deluge system. Hydraulic calculations and sizing of the pipe for system demand will show how much water is being used based off of system demand and what is still available via the supply. You don't need to account for the additional leftover available water unless its a water storage tank design with refill rates or hangar supplying a foam systems.
Reply
Justin Milne
2/11/2021 11:52:18 am
At what pressure are is water hammer going to start to be an issue? Only have 70 psi currently and normally don't have issues with water hammer. Pump startup would jump that 70 psi to 184 psi.
Reply
Franck
2/12/2021 02:48:55 am
Just one comment on waterhammer.
Reply
Franck
2/12/2021 02:58:04 am
Another additional comment to emphasize the excellent explanations by Dan.
Reply
10/18/2021 01:59:17 am
Hi,
Reply
6/15/2022 05:03:29 am
Thank you so much for this article! This was exactly what I needed.
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop November '24 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
December 2024
PE PREP SERIES |