My jurisdiction (I am the AHJ) has had several buildings built with private hydrants supplying the sprinkler system where the main comes into the building, through the RPZ, feeds the sprinkler system/standpipes, and leaves the building and feeds the hydrant(s). This has always seemed counterintuitive to me, at best. I feel we are "robbing Peter to pay Paul" and have wondered if this arrangement will adequately supply the sprinkler system when we (FD) pull water from the hydrant and pump it back into the FDC.
Per our state law, private hydrants have to be "protected" with a backflow. Is this configuration code compliant, and if not, what is a solution? Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
14 Comments
Pete H
3/4/2025 06:34:32 am
It really should be fed off a bypass line instead of going through the double check for a cleaner install imo.... but as long as the hydrant can calculate the required water and meets code in every other way, a private hydrant can be fed from main that goes through a building.
Reply
Dan Wilder
3/4/2025 06:59:50 am
While not common, if calc's prove it works I see no code-based opposition. Review of the max flow through the backflow to confirm sprinkler and hydrant demand does not exceed the max flow (plan on one or several increases in sizing to accommodate max flow or valves in parallel).
Reply
Mike Morey
3/4/2025 08:14:37 am
In the cases where we've done this we've ensured that there is still a city side hydrant near the FDC and only used it for hydrants beyond the pump/riser room. Large building loops are built this way all the time at spec/shell/warehouse buildings. Biggest issues are ensuring you can provide the required site fire flow or portion there of the AHJ wants from the hydrant(s) and accounting for the hydrants connection point as your hose stream demand point in the sprinkler calc.
Reply
Joe
3/4/2025 08:38:09 am
Not normal but you would have the same issue if after the back flow device you install underground piping with hydrants spaced per you code and then somewhere you have a leadin going into the build for the sprinkler systems
Reply
Casey Milhorn
3/4/2025 08:42:27 am
What Mike M said... typically I suggest a public hydrant as the hydrant used for the pumper truck. Also what Pete said, a bypass line WITHOUT a control valve would be best in my opinion. That way you still have hydrant flow if the backflow is out of commission and valves are closed off. It appears as if you might have a decent size building and I would be concerned that you would be able to meet your fire flow demand through that backflow, not to mention the amount of pressure loss across a RPZ will be considerable. With a 6" Wilkins 375, you are maxing out it's listing at 1,500 gpm. I would imagine your fire flow demand is at least 1,500 gpm.
Reply
Glenn Berger
3/4/2025 08:55:22 am
As long as the system supply can support the maximum expected flow through sprinklers and the exterior hose connections that the layout seems acceptable.
Reply
Anthony
3/4/2025 09:09:01 am
this appears to be legal with an RPDA/RPZ however, the calc's will get more difficult as the hose allowance will have to be take out after the water has passed by the supply for the sprinkler system. I think this may cause over sizing on the sprinkler system you'll want the hydrants that to tee off prior to the system supply.
Reply
DJT
3/4/2025 10:19:03 am
The hydrant supply needs to be separated from the FDC. As it's shown the FD pumper will circulate water from the hydrant and pump it back through the FDC as the arrows indicate. This risks checking the incoming water supply back until the sprinkler discharge drops the system pressure, rendering the FDC/pumper useless. The two solutions are either tee off to hydrant from upstream of the FDC tee while adding another check valve between the two connections, or move the FDC to tie into each riser above their check valves. Some problems don't have code justification.
Reply
Jack G
3/4/2025 10:56:00 am
First of all I would add an fdc check to each of the sprinkler systems and a check at the end of the manifold before the tee going to the hydrants. Then I d tie the checks into one fdc.
Reply
Jack G
3/4/2025 11:02:28 am
And you could add an fdc to the far side of the building ( bulk and check) to use in combination with the wall hydrants and common fdc.
Reply
Jack G
3/4/2025 11:06:10 am
I would also use OS&Y Valves on each side of the rpz with the appropriate tamper switch instead of the gate valves shown.
Reply
Jack G
3/4/2025 11:13:54 am
Of course the fdc shown would not be tied in where shown but after the 5 checks added ( tied into 1 fdc , and or another on far side of the building) and I d make the fdc a storz and or 6 inch fdc, for the hydrants .
Reply
Ed
3/4/2025 12:22:12 pm
DJT is correct. The current arrangement will not work. The fire hydrant supply has to be before the tee for the FDC with a check valve in between. Otherwise, the system will not pressurize appropriately since you are recirculating the flow.
Reply
Mark Harris
3/5/2025 03:18:54 pm
Great comments. Made me think about a distribution center that could have a booster pump or pump and tank fed from city supply with FDC on the pump house and as noted the pumper truck supply for FDC would need to be a supply hydrant before the pump house. Then could have private underground loop with private hydrants and supply into building for sprinkler risers.
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop Feb '25 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
March 2025
PE PREP SERIES |