My company just completed design/build construction of a canopy structure over a courtyard between two restaurant buildings located on the east & west sides.
We assigned an Occupancy Classification of A-5. The structure is all steel, other than the roof construction is comprised of the following layers: 22 gauge steel B deck, 7/16 inch OSB, 24 gauge metal standing seam. The standing seam contractor asked for a solid substrate, instead of metal to metal (Standing Seam attached to the B Deck. We agreed to add the OSB. We examined the 2018 IBC and assessed that we could use the OSB. Our assessment concluded that the entire structure could be built with wood framing without sprinklers (A-5, no enclosures, height 37ft, 6,090 sf, Type V(A) Construction). The AHJ shut us down and told us we needed to remove the OSB (combustible material). What we didn't know was that the City and developer executed a Covenant Agreement that stipulated the Canopy was an A-3 Assembly occupancy. This was arranged because the developer didn't want the exterior restaurant walls to be fire-rated because of the ease of movement from the restaurant to the courtyard. As a result, the OSB needs to be changed to fire-retardant-treated plywood. Was the original classification of A-5 occupancy (which could have been wood) canopy assembly an acceptable approach? Picture below, showing the galvanized steel deck. Sent in anonymously for discussion. Click Title to View | Submit Your Question | Subscribe
13 Comments
Chad
3/24/2025 07:58:48 am
What did you, or someone else do to tick off the FD?
Reply
Glenn Berger
3/24/2025 08:40:26 am
Assembly Group A-3 contains the "other assembly uses not classified elsewhere" provision.
Reply
Jerry
3/24/2025 08:49:50 am
The canopy roof top has a 97kW solar array. The solar was apart of the development approval. Activities beneath the canopy include table seating and NG fire pits with an occupant load of 100.
Reply
Ricardo Gonzales Jr
3/24/2025 09:00:37 am
When taking on a project, always ask what the Architect has defined the space as. As you learned later, the Architect had already defined the space with the Building Officials but appears they didn't pass that information to you or your team.
Reply
Jerry
3/24/2025 09:18:20 am
The Covenant Agreement between the City and Developer (assigning the A3 Occupancy) occurred after we were presented our contract (no mention of A3). Additional question - an A5 assembly is the only assembly (A1 thru A5) that is considered open…is this correct?
Reply
Ricardo Gonzales Jr
3/24/2025 10:46:38 am
In my opinion, it would appear the closest set of Assembly that fits the situation. As with outdoor arenas, they have large shade overhangs for the spectators, and I would gander that they would have more than restaurant sitting going on. I've been to a few restaurants who had entertainment going on outside for the clients. They didn't have such a cool, statement, shade structure outside of their A-2 building. Far better than what the Romans were capable of with their coliseum.
Jack G
3/24/2025 09:17:46 am
Could you sell them on limited combustible.
Reply
Conrad
3/24/2025 03:29:00 pm
Missing info on occupant load, exiting, existing fire protection of the two buildings. However, probably not needed as there is an agreement specific to this location. It reads like the courtyard is being used for outdoor events/seating/overflow for the two restaurants. A 6,000 sq ft space can hold a lot of people. Depending on occupant loads, if the two restaurants share exit components with the canopy, it may require a fire sprinkler system.
Reply
Jerry
3/24/2025 08:17:15 pm
The canopy space has an occupant load of 100. The 2 restaurants (A-2) are sprinkled. The north and south sides beneath the canopy are open (56ft wide). Only one restaurant can exit into the space beneath the canopy. Using IBC Chapter 10, Section 1005.1 Minimum Required Egress Width: using .2 inches (width) per occupant…assuming 1,000 occupants (actual combined total 1 restaurant + 100 beneath canopy…not even close to 1,000), this load would require (1,000 x 0.2)= 200 inches or 16’-8”.
Reply
Todd E Wyatt
3/24/2025 11:41:01 pm
Your statement ...
Reply
Jerry
3/25/2025 05:33:41 am
Todd,
Reply
3/25/2025 11:28:20 am
I see no separation from the other structures; so these three structures appear to be one "building" in accordance with the IBC.
Reply
Jerry
3/25/2025 02:24:50 pm
Paul,
Reply
Leave a Reply. |
ALL-ACCESSSUBSCRIBESubscribe and learn something new each day:
COMMUNITYTop March '25 Contributors
YOUR POSTPE EXAMGet 100 Days of Free Sample Questions right to you!
FILTERS
All
ARCHIVES
April 2025
PE PREP SERIES |